PROGRESS MADE & PRESENT POSITION
NEXT QUARTER TARGETS
(a) To establish a controlled tip
for solid waste at Sai Tso Wan, near Kwun Tong, to commence operation by April 1977.
(b) To establish a solid waste
baling plant adjacent to the controlled tip at Sai Tso Wan by July 1978.
(o) To establish a controlled tip
for solid waste for the Eastern New Territories.
(a) To establish a controlled tip
for solid waste for the Western New Territories.
(a) A Housing Department licensed area
occupies the site. Clearance of this is in hand by stages and is expected to be completed by June 1977. Site formation work is to be completed by April 1977.
(b) Similar clearance problem as with 1.
above. Phased clearance is to make the area available for site formation work by June 1977, constructions of plant to commence by Sept. 1977, and plant to commence operation by mid-1978.
(c) Due to impending closure of existing controlled tip at Shuen Wan near Tai Po, site for new tip must be agreed by December 1976. S.N.T. is considering possible sites.
(b)
(a) Liaise with P.W.D./
H.D./U.S.D. to ensure no delay in clearance and site formation, to enable the tip to commence operation on schedule in April Liaise with P.W.D./ H.D./U.S.D. to ensu no delay in clearan construction and sit formation, to enable the plant to commen operation on schedule by July 1978. (c) Agree site by end
(d) New site required, to handle additional (d)
solid waste to be generated in Western New Territories and to replace existing tips at Ma Tso Lung and Siu Lang Shui which will be full by 1983.
CONFIDENTI
December 1976 and ensure that planning proceeds on schedul
Agree site by April 1977 and ensure that planning proceeds on schedule.