The results of these simulation tests, showed that the

expansion pattern postulating a new power station of 4 x 350 mw generating sets was least expansive. This indicates that the savings in capital cost (per kw installed) of

350 mw sets are more than the increase in costs needed to

provide additional reserve capacity and spinning reserve.

Further, it can be seen from the table below that the

economic order of merit of the three expansion patterns

remains the same whether fuel escalation costs are taken

into account or not.

Fuel Escalation Cost

New Power Station Capacity

Present Worth Cost

for 1981-2000

HK$M

Additional Present Worth Cost Compared With the Cheapest Pattern

Total

Capital

% of Capital

HKEM

Cost

Cost

4x200 MW

17943

3993

297

7.7

5% p.a.

4x275 MW

17799

3979

153

4.0

4x350 MW

17646

3843

1

4x200 MW

11673

3993

257

6.7

None

4x275 MW 11585

3979

169

4.4

4x350 MW 11416

3843

Accordingly it is intended that the first phase of

development of the new power station will consist of

4 x 350 my sets installed in accordance with the time

the memorandum..

scale set out in para. 8