In
solutions and proposals that would
adequately meet the Provisional Authority's
design and performance requirements.
spite of constant requests from the
Provisional Authority it was not until
mid-November 1974, nine months after
the signing of the Letter of Intent,
that the Consortium produced a package
of design solutions. This package,
which the Consortium called a "Basic Plan",
has been thoroughly examined by the
consulting engineers, the Mass Transit
Department of the Public Works Department
and the engineering officers designate
of the future Mass Transit Railway
Corporation. The design solutions and
proposals proved to be inadequate and
incomplete compared with the Provisional
Authority's specifications and, in some
cases, unsuited and even irrelevant to
Hong Kong's conditions. The spokesman
said that "in all the circumstances, it
is not possible for the Provisional
Authority to reach any conclusion other
than that the Japanese Consortium has
acted ineptly or in bad faith."