(6)
M & E:
European labour
%
European materials
•
.%
Hong Kong labour
Hong Kong materials
•
·
+
Annual increases beyond these levels are to be construed as
events of force majeure and compensated outside the ceiling
price. As already agreed, compensation for any other event
of force majeure is to be outside the ceiling price, (It
will be noted that with this form of contract, escalation
charged would be that actually taking place and not that
assumed in calculating the ceiling price, hence the
possibility of a final contract price lower than the ceiling
price).
Alternative Two
Under this alternative we now bid a contract price of HK$
This contract price is also a ceiling price except as regards the
part of the contract payable in HK dollars, which is to be
adjusted as set out below.
The contract price represents the
sum of several lump sum prices, respectively for the civil
works and for the complete M & E works and supplies (certain of
which such as the ventilation system will be assessed at this
stage as provisional sums); in each case covering adverse
physical conditions and quantity overruns, The contract price
also covers all European escalation, based on the following
annual increases:
3