0003160 G.F. 316
20
as follows:
(a)
SECRET
4
Original estimates provided by the Group
Add costs of:
Chater Station and line to Admiralty
(figure for civil works provided by the British Group; figure for E & M assumed by MTSG)
231
HK$ mn
4,047
Demolition and underpinning (figure
provided by the British Group)
10
Cooling water supply and disposal for
station air-conditioning
25
Change of construction method to suit
limited working room (figure
provided by the British Group)
47
Miscellaneous items
18
331
4,378
P
Add contingencies (15% for civil works
and 7.5% for E & M
483
4,861
Less original provisions made by the
British Group for:
Contingencies
432
Project management, insurance, etc.
241
673
4,188
Add:
Exchange rate adjustments (cf.
paragraph 6 above and paragraph 22 below)
(-)292
Provision for unforeseen
circumstances
500
Project management, insurance, etc.
308
Cost escalation from mid-1972 to
date of completion of construction (at 8% p.a.)
1,785
2,301
Assumed contract price
6,489
The column headings used in the cash-flow table are explained
the Corporation's own cost consists of:
(i)
land acquisition costs, estimated at $200 mn at mid-1973 prices, less possible resales of surplus land estimated at $50 mn at mid-1973 prices;