information on soil conditions would be made available by the Consulting Engineers progressively as it is ready;

(c) other basic data and design parameters for civil works

and performance specifications for E & M supplies would also be made available progressively; and

(d) negotiations on the contract would be completed by the

end of March 1974.

Part II

day

Explanatory Notes on the

Cash Flow Table in Part III

The cash-flow table in Part III of this Annex has been drawn up on the basis of Intermetro's proposals and of certain assumptions made by the Mass Transit Steering Group.

17

Intermetro's price estimates (see paragraph 5 above) have been adjusted as follows to bring them roughly in line with the coverage of the prices indicated by the other three consortia:

Original estimates provided by

Intermetro

Add costs of:

HK$ mn

2,573

Chater Station and line between

Chater and Admiralty

139

Cooling water supply and disposal

for station air-conditioning

25

Supply of aluminium (as opposed to

steel) rolling stock

21

Temporary decking (additional provision)

12

Preliminary expenses: training

14

Miscellaneous items

15

226

2,799

Add contingencies (15% for civil works

and 7.5% for E & M)

Less original provision made by Intermtro

for management fees

Add:

Exchange rate adjustments (cf.

312

3,111

191

2,920

paragraph 5 above and paragraph 20 below)

40

Provision for unforeseen circumstances

500

Management fees (adjusted in relation

to the higher contract price)

296

Cost escalation from mid-1972 to date of completion of construction (at 8% p.a.)

1,325

2,162

Assumed contract price

5,082

SECRET

/.... 18