information on soil conditions would be made available by the Consulting Engineers progressively as it is ready;
(c) other basic data and design parameters for civil works
and performance specifications for E & M supplies would also be made available progressively; and
(d) negotiations on the contract would be completed by the
end of March 1974.
Part II
day
Explanatory Notes on the
Cash Flow Table in Part III
The cash-flow table in Part III of this Annex has been drawn up on the basis of Intermetro's proposals and of certain assumptions made by the Mass Transit Steering Group.
17
Intermetro's price estimates (see paragraph 5 above) have been adjusted as follows to bring them roughly in line with the coverage of the prices indicated by the other three consortia:
Original estimates provided by
Intermetro
Add costs of:
HK$ mn
2,573
Chater Station and line between
Chater and Admiralty
139
Cooling water supply and disposal
for station air-conditioning
25
Supply of aluminium (as opposed to
steel) rolling stock
21
Temporary decking (additional provision)
12
Preliminary expenses: training
14
Miscellaneous items
15
226
2,799
Add contingencies (15% for civil works
and 7.5% for E & M)
Less original provision made by Intermtro
for management fees
Add:
Exchange rate adjustments (cf.
312
3,111
191
2,920
paragraph 5 above and paragraph 20 below)
40
Provision for unforeseen circumstances
500
Management fees (adjusted in relation
to the higher contract price)
296
Cost escalation from mid-1972 to date of completion of construction (at 8% p.a.)
1,325
2,162
Assumed contract price
5,082
SECRET
/.... 18