Draft Minute tor

The Prime Minister's Office

For the signature of:

The Private Secretary to

The Farliamentary Secretary

Tons Lone Tunnel

This project was until the events of last year entirely

a private vonture in Hong Kong. Tho Covernment of Hong Kong

at first refused to participate except es a minority shareholder

and its current participation is that of a private phareholder

with a 25% interest in the equity. There is reason to believe

that the Hong Kong Coverment does not regard the project as

having a high priority in the Colony.

2.

E.C.G.D. have to considor the application for a guarantee

of a lean on its merita es an underwriting proposition. Tho

borrower, the Hong Kong Turnol Company, is a private company whoso

capital (when subscribed) will still leave 75% of the contract

valus to be paid from the loan. The Company has throughout sought

to obtain the loan finance with no other cocurity that the proc-

pective earnings from the operation of the turmal. E.C.G.D. has

never been authorised to guarantee investment of this natura.

In accordance with its normal practice in such cases the

Department has sought adequate guaranteos.

3.

It is common practice world-wide for publio corvico projects of this nature to to guaranteel by the govermont of the buying

country. Either this, or in soze countries a Central Dank

guarantee would be required as a condition for taking the entire

rick on a cum of £12 million.