September_1967 — Page 7

Far East Builder 遠東建築雜誌 All

e) Film filing rooms, f) Reporting room. g) Conference room. h) Ancillary room.

Site

The new operating theatre block was erected on a limited area in the rear court yard of the existing main hospital building, It is the only site adjacent to the hospital which could be developed without seriously affect- ing the existing amenities.

The site subsoil was rocky in na- ture and in order to minimise the considerable noise arising from the removal of rock, the bottom of col- umn footings was raised to the high- est possible level.

Building

The height of the new block is kept to a level not higher than the existing hospital block in order not to affect to a great extent the light and air to the wards in the adjacent wings. The shape of the block is governed by the requirement of the operating theatre suites and each suite, forming a "cul- de-sac department. is so planned to have easy access to the wards it

serves.

The operating theatre suite is divided into steriled zone, clean zone. and dirty corridor so that the chances of cross infection are minimised.

The radiodiagnosis block was erected in the court yard in front of the hospital, supported on columns over the parking area and connected to the existing main hospital build- ing at first floor level. The five ma- jor X-Ray rooms are grouped as satel- lites around the central dark room and viewing room where both manual and automatic processing units are provided.

Services and Equipment Air-conditioning installation

Due to the difficulties in obtaining fresh or salted water for cooling, an air-cool system has been adopted for the air-conditioning installation for the operating theatre and radiodia- These blocks are fully gnosis blocks. air-conditioned for year round com-

fort.

Temperature. humidity and air movement are designed to suit the conditions called for in each in- dividual section. 100 per cent of out- side fresh air is provided for the oper- ating theatres, at the rate of 15 com- plete air changes per hour. The air is drawn into the cabinet which hav- ing a pre-filter and a fine filter, is cap- able of removing 99.9% of the germ carrying dust particles down to five microns.

Electrical installation

For the normal supply two new 1,000 KVA transformers have been provided to cope with the demand for the whole hospital compound. An M.V. Board of 13 panels, manufac- tured by Wallace Town Engineering

Radiodiagnosis block and air-conditioning plant building (left) seen from hospital approach road

Co. Ltd., has been installed for medium voltage.

An emergency generator of 450 KW 3 phase 346 V has also been in- stalled to cater for the essential load required by the hospital. Emergency batteries are provided for essential lighting in operating theatres and main switch room.

Operating theatre lamps

Hanau Operating lamps (model Stockholm)

Hanau Minor Operating lamps (model Cologne)

Medical gases

Piped oxygene, nitrous oxide, vacuum and compressed air to each operating theatre and other places where such installations are required. Sterilizing and other equipment

Operating theatre sterilized room: High pressure autoclave; bowl and instrument boiling sterilizer; heated cabinet for bottle fluids; and formalin cupboard.

Central Sterile Supply Dept: Two high speed high vacuum autoclaves;

Far East Architect & Builder September, 1967

sor

Waterstill (Mascarini Thermocompres- still 50 gal. hour); Infra-red sterilizer; and hot air ovens.

Pharmacy: Two ultra sonic clean- ers: Rapid cooling fluid autoclave: hot air oven: glove cleaners; and portable autoclaves.

Automatic

Radiodiagnosis block: processing unit (Kodak X-Omat); and manual operated film processing unit. Telephone installation

PABX system with 300 extensions has been installed to replace the old PBX system.

Calling System

A new staff location system oper- ates on an induction loop having 180 channels.

Microphone installations are pro- vided between teaching operating theatres and observation galleries.

Building Time

Work started in February 1965 and was completed in March 1967. a period of 28 months.

31