No_4_1955 — Page 24

Far East Builder 遠東建築雜誌 All

(Above) The stadium at its present

stage of completion.

(Right) As it will look if expanded

to its greatest capacity.

The Pavilion will house the dressing rooms and club amenities as well as pro- vide accommodation for 550 patrons. The score board and 10 ft. diameter clock are

located at upper terrace level at the southern end of the ground. One of the lisadvantages of the site is that unautho- rised views can be obtained from the sur-

rounding hillsides, This will be partially offset when funds permit the complete covering of the seating terraces.

Construction

The bot-

Before forming the site, the existing Olympic Stadium in Sweden. Built up in nullah running the full length of the stadium site had to be first repaired and then covered over with reinforced concrete slabs with appropriate manholes spaced at regular intervals and built up as the work of filling and consolidating proceeded.

3 separate layers, the overall consolidated tom layer, 6 inches in depth, is composed depth of the track is 12 inches.

of 2 inches granite aggregate and the middle and top layers of inches and 2 inches depth respectively, composed of a mixture of screened cinder and loam in their respective percentages. The playing field has been top dressed with 8 inches of black soil obtained from the site, and the turfing carried out by the Gardens Dept. of the Government.

a

an

tem and telephone communication system controlled from this box is provided to assist in crowd control.

Economics of Design

The whole scheme was designed with the object of utilising, as much as pos- sible, the material found on the site. All construction work, such as walls, terrac- ing, manholes, gutters and channels etc.. were executed in cut granite stones set in cement mortar. All top and black soil used for the turfed area was supplied from the existing Government nursery gardens. the gardens being re-sited elsewhere, A portable stone crusher on the site gave more than the necessary aggregate and "fines" for the cement concrete to be used. It was thus possible to obtain a very low contract price for the construc- tion of the stadium.

Other Details

Owing to the great depth of consolidat- foundations of the pavilion were ed filling required at the north end, the

tructed before filling commenced in order to obtain a solid bottom and reduce costs.

and a new

cons-

portion of their ground. Alternative sites were also found for the Hindu Crematorium and Chinese Farewell Coffin Pavilion. which was formerly located at the north end of the valley.

Due to the erosive action of the sand

The existing Tung Wah Eastern Hos- brought down by the fast flowing water

pital Road has been raised approximately of the surrouding hills, the existing cement

20 ft. above its previous level, bringing it concrete nullah at the south end of the

to approximately the same level as Caro- site had to be replaced by a new nullah,

line Hill Road, The 20 ft. mass retaining It was necessary to construct a more re

wall separating the 40 ft. wide reconstruct- sistant wearing surface to prevent future

Advantage was taken of the stream ed road from the I.R.C. grounds runs erosion. This was accomplished by encas- which flows down the valley to construct practically through the centre of the old ing 6′′ granite sets in 1:5 cement concrete

small dam and a 50,000-gallon water I.R.C. clubhouse which was demolished bedded on a 1:9 cement concrete base.

This tank will ensure storage tank.

one built in the north-west The formation of the site involved the adequate supply of water throughout the excavation of some 160,000 cu. yds. of year for watering the football field and earth and decomposed granite and 100,000 running track, cleaning the terraces and cu. yds. of rock. The rock excavation provide a flushing supply for the 17 toilet presented a difficult problem due to its blocks. extremely hard nature and as a result

The roof over the central western section

In keeping with the present popular progress in construction of certain sections of seating terraces was impeded.

7 bays of seating and comprises trend of staging sports events in the even- Some

the fabrication and erection of steel trusses ings, a scheme for providing floodlighting 200,000 cu. yds. of the excavated mate- rials

supported on 12-inch circular steel frontal is at present being considered. were used on the site as fill, and columns 22 ft. high and 12 inch by 8 inch consolidated by a sheepsfoot roller drawn steel joists at the rear.

The whole site, including parking facili- The overall span ties for some 400 cars, occupies an by a 10 ton crawler tractor, thereby re is 93 ft. with cantilevers of 38 ft. and 7 of over 16 acres. taining the natural moisture content of ft. at the front and rear respectively. The roofing materials consist of asbestos The whole area of the field and running cement corrugated sheets. Advantage was track is drained by a network of 6-inch taken of the excellent vision obtained at and 4-inch agricultural tiles arranged in roof level to construct two radio boxes to herringbone pattern,

pattern, and overlaid by a enable on-the-spot_commentaries of any specially designed filter media composed sporting events to be broadcast from the of graded granite aggregate. The specifi- stadium. In addition an observation box cation for the cinder running track follows has been constructed for the Police Depart closely the one laid at the Stockholm ment and a modern Public Address Sys-

the excavated material.

covers

22

Future Extension

area

The planning and designing of the Stadium has involved much careful thought, and the designers have not overlooked the possibility of a further extension of accom- modation which might become necessary if Hong Kong should be chosen at sonie future date as the venue for international sporting events. In this respect by ex-

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.