PLAN
SCA L
150
100
200 FT
PRINCESS #
MARGARET
ROAD
PERTH ST
ARGYLE ST.
WATERLOO RD
D
ARGYLE
ST
WATERLOO
ROAD
Preliminary Design
Preliminary design work was com- menced late in 1963 with a scheme to provide a two-lane 24 ft. wide flyover from Princess Margaret Road to Waterloo Road passing over the complex and the junction with Perth Street, with a total length of ap- proximately 1,300 ft. including two ramps.
Early in 1964, however, it was decided to construct а three-lane/ carriageway to provide a two-lane one-lane tidal flow, which the traffic surveys indicated would be required when in full operation. Owing to the very restricted road width available in Princess Margaret Road it was
necessary to lengthen the flyover to 1,681 ft. in order to provide for the 33 ft. wide carriageway.
Site Investigations
It was known that a number of large pipes and sewers lay along the alignment of the proposed flyover, as well as a multitude of small drains, cables and ducts. To obtain accurate information on their alignment and levels it was decided to have trial holes excavated at each pier position prior to percussion borings.
Disturbed soil samples were taken and standard penetration tests were carried out at about 10 ft. intervals or at "change of soil". The samples
indicated that decomposed granite underlay sand and fine clay at depths varying from 10 ft. to 40 ft. below ground level, with the water table about 12 ft. below ground level.
Design
The basic outline shape of the piers was governed by the restrictions imposed by the limited road width available.
The main design considerations made were as follows:——
(a) A minimum clear headroom of 16 ft. 6 in. below the fly-
over.
(b) Single centre support
CAST-IN-SITU R C BEAM
PRESSTRESSED BEAM OR UNIVERSAL STEEL BEAM
RC.C CANTILEVER BEAM 4 ́DIA DRAIN PIPE INSPECTION EYE
58
IN
• CONDUIT AT CIC
DETAILS OF PIER PROFILES
CARRIAGEWA
FULL SUPERELEVATION ON CURVES
R.C.C. ROAD SLAB (CAST - IN – SITU)
L.C.C❘ PIER
3 CA
+
4
& FT
# CC PILE CAP
2020 VANES
X
I
(APPROX.)
L-o
WAT
!
(c)
Design speed 30 m.p.h.
(d)
Max. gradient 1:15.
ft.
(f)
(e) Minimum horizontal radii 238
Minimum vertical curve 200 ft. length. (g) Loading
loading
M.O.T. H.A.
The horizontal alignment was practically predetermined in that the flyover had to be carried above the existing roadways, while the vertical profile was controlled by the clear- ances required at the main complex, Perth Street, and by the road width restrictions at the southern end of the project.
A scheme was prepared with 35 ft. spans, except at the three major crossings where 60 ft. spans were proposed. Using these spans, normal reinforced concrete I-beams were proposed for the short spans with prestressed I-beams for the 60 ft. spans. The design calculations show- ed that the construction depths for both forms of construction were al most identical so that a smooth soffit profile was achieved.
A second scheme was also pre- pared using 55 ft. equal spans with prestressed I-beams on all spans, but utilising the cast-in-situ road slab to act as a composite structure.
After considerable detailed exa- mination of both schemes had been
Far East Architect & Builder May, 1966
No comments yet.
Private notes are available after approval.