sunk in position on a prepared founda. tion.
A steel caisson with concrete base slab as ballast has been constructed at Taikoo Dockyard. After launching, the caisson will be completed internally to provide the reinforced-concrete sub- structure to the ventilation building. This will increase the draft of the cais- son which will be completed and sunk in position on a prepared crushed- stone bed. The laying of the sub- merged-tube tunnel will start from this building once it is in position and ready.
All work on the South ventilation building and ramp will be constructed in the dry within a temporary earth and rockfill cofferdam (Fig. 4). The ventilation building will be of conven- tional reinforced-concrete construc- tion while the ramp will be a rein. forced-concrete twin box where it is covered and a reinforced concrete U- shape where it is in cutting.
The open section will have to be anchored down against flotation by means of prestressed anchorages.
Tunnel units
There are two principal systems for a submerged tube tunnel: either a
TAWAG "WAWANAWAKA
INININININIRIKIK.
North ramp open section during construction
structural steel unit which is launched like a ship and then lined with rein- forced concrete or a rectangular rein- forced concrete section which is com- pleted in dry dock and then floated out. The former, which is the system being used in Hong Kong, is usually constructed in a shipyard, while the latter is usually constructed within a specially-formed cofferdam.
If there is anything unique about the Hong Kong tunnel, it probably is
that a conventional shipyard has not been employed to fabricate the steel units. Instead, a temporary fabricating yard complete with slipway has been set up specially at Hung Hom adjacent to the line of the tunnel. A plan of this yard is shown in Fig. 5.
First, steel plate 36ft. x 6ft. 3/8in. is unloaded across Hung Hom seawall and stacked ready for use. Next it passes through straightening rolls and then on to a Hancoplater which con-
зу
oll plaza
"
King's Park
Ferry piers
ག་ས་ནི་་་་་
HOL
OOC ПП
Hung Hom
4000
1 Mile
5000 feet
Far East BUILDER, June 1970
R.C.struts
light louvres
R.C, struts
Fig. 2. Typical deep (louvred) section
R.C. arches
precast concrete facing unit
4'-0" dia. contiguous bored piles
ventilation duct
R.C. struct
Base slab varies 4' 9"
5' 9" thick
4'-0" dia. contiguous
bored piles
Fig. 3. North ramp
cut and cover
29
No comments yet.
Private notes are available after approval.