VERTICAL LINED WALL
COLLAPSIBLE DAM
CONCRETE BOTTOM
VIEW -
COLLAPSIBLE DAM
CAN ALSO BE USED IN WATER COURSES WITH SLOPING BANKS
RESERVOIR WATER,
COLLAPSIBLE DAM WATER INFLATED
SECTION A-A
GA ANCHORING BOLT WITH HEX NUT, STAINLESS STEEL APPROX 16 in C/C
CONCRETE BOTTOM
7% in STUD WITH HEX NUT, STAINLESS STEEL WELDED TO STEEL PLATE. APPROX 4 C/C
-415 PIPE SPLIT &
WELDED TO
CHANNEL
COLLAPSIBLE DAM
fastened together end to end and controlled as one unit.
In order to handle the various strength requirements for different heights of Fabridams a range of fabric constructions has been devel- oped. The basic difference between the constructions is the strength usually determined by the quantity of fabric plies laminated into a sheet. The table below shows several stan- dard constructions and some of their physical properties:
Above: View of junction between "Fabridam" and side of water course Below: Detail "D," showing attachment of dam to side wall
CONCRETE FILLED
CHANNEL
A
WATERCOURSE OR
SPILLWAY WALL
RUBBER STRIP
-VENT HOSE
STEEL PLATE CONCRETE BOTTOM
Vain DIA SOLID RUBBER SEALING BEAD
Construction
Wt lb/yd2
Punture Resistance
Ultimate Breaking
ia
Strong th
Min STEEL PLATE
lin DIA REINFORCEMENT STEEL
·ROD WELD TO LIN DIA STAINLESS STEEL STUD
Pounds
Ib/Lineal in
1-Ply
4.5
190
700
.COLLAPSIBLE DAM“
CHANNEL
2-Ply
8.3
370
1,400
DETAIL C
3-Ply
10.8
525
1,870
4-Ply
13.3
550
2,200
DRAIN LINE WITH WALVE IN SUMP
IN CONCRETE BOTTOM
FILL UNË
GROUND LEVEL
· BLOW-OFF LINE WITH REMOTE CONTROL WUYỀ
AND STAND PIPE
SWIVEL GOOSENECK FOR ADJUSTING HEIGHT OF DAM LA FUNCTION OF HEADHIMI]
Standard inflating and deflating pipework
DRAIN DOWN STREAM
tion of fabric plies. In its inflated operational state with water over- topping carrying sand and debris, its functioning compares physically to that of a tyre running at a moderate speed on a rough road. Because of its lower inflation pressure it is more resilient than a tyre, enabling a high rate of deflection of foreign materials, resulting in less damage.
The inflation cycle is a simple and reliable one. Regardless of whether the inflation medium is water or air, storage tanks can be installed adja- cent to the Fabridam with sufficient capacity to ensure complete inflation whenever required. Many alternate methods and sources can be utilised in water inflation, such as gravity flow, artesian wells, or forced feed by pumping. In the case of air, a
Enlarged view of part section A-A dam anchorage
unit. In this manner, by installing separate controls to each unit, a greater flexibility of control can be attained.
Another useful appliclation of the Fabridam is the fact that is can be placed on top of existing dams to increase reservoir capacity or, in the If concrete abutments are not case of power schemes, to increase wanted, individual segments can be the potential head available.
Asphalt Surface on all Thailand Roads
ALL highways in Thailand will have an asphalt surface under a five-year plan by the Government's Highways Department.
During 1965 the department plans to have work started on eight high- ways in South Thailand. Contractors have been named for three of these and the other awards are imminent.
The schemes include:
Trang-Cantang, 12.59 kilometres. Award to Visvanamita Co., 4,466,344 baht.
metres. United Engineering Co., 21,944,686 baht. Completion period two years.
Tabsake Chumphon, 115 kilo- Tenders being considered. Work will take three years.
metres.
Nakorn Sawan - Tak (Wangchoo- Tak), 23.63 kilometres. Tenders just received. Contract to take one year. Chandburi Trad, 58.10 kilo-
metres. Bids being studied. Two year
contract. Work to be completed within
one year.
Huey Yord Krabi Pang-na, 133.24 kilometres. Tenders being studied. Three years.
Roi-et Completion
Saraburi-Lopburi-Singhaburi, 54.32 kilometres. Award to Vorawatena Co., 17,340,000 baht. period is two years.
Nakorn Sawan
Tak (Nakorn Sawan Wang Chao), 64.44 kilo-
——
Yasathorn Ubol, 19.94 kilometres. Tenders to be invited this month. Work to be completed in one year.
high volume - low pressure blower Contract to Straighten River
can be used.
At Tai Po Tau the dam is fastened in place to a reinforced concrete slab and foundation with structural steel members and anchor bolts.
Heights
The present height limitation for a Fabridam is approximately 20 ft. However, new materials in the de- velopment stages will allow 30 ft. heights in the near future. While
there is no limitation on lengths, from the standpoint of economics in shipping and handling during instal- lation, units would not normally ex- ceed 400-500 ft, in length.
When requirements call for longer dams the procedure is to use vertical concrete abutments between each
72
A CONTRACT worth M$2,326,000 has been awarded to Salvage Engineers, Ltd. for straightening the mile-long winding Kallang River and Sungei Whampoa in Singapore.
The realignment is part of the $25 million Kallang reclamation scheme which will yield 300 acres of land for development. When the Kallang river is re-channelled, it will run in a straight line from Serangoon, join up with Sungei Whampoa near Ar- thur Bridge in Geylang and flow in- to the sea at Merdeka Bridge.
The scheme entails dredging at several places and
places and building con- crete walls on both sides in order to prevent erosion.
Reclamation work in Kallang started about seven months ago, and
by the
end of last year about 80 acres had been reclaimed. The Housing and Development Board had spent about $5,000,000 on re- clamation by the end of last year.
Progress on the scheme is linked with the progress of developing Toa Payoh as a satellite township. The Board has built a temporary road from Tao Payoh to Kallang to transport earth to the reclamation site.
Construction tenders for the Muda River Project in Malaya, described in the January issue, are now being invited by the consulting engineers, Sir William Halcrow and Partners. See advertisement page 66.
Far East Architect & Builder February, 1965
Page 40Page 41
No comments yet.
Private notes are available after approval.