Head 42-KOWLOON-CANTON RAILWAY
Estimate 1967-68
Other Charges Contd.
II
SPECIAL EXPENDITURE
LA
85
Approved Estimate 1966-67
$
$
13
14
Additional loop line at Lo Wu
Additional waiting shelters
253,000 h 105,000
577,000
15 Battery chargers
4,000
16
Equipment for railway workshops
109,400
15292 2838385
17
Fence at Beacon Hill Tunnel
10,000
18
Improvements to lighting at Lo Wu
13,700
Improvements to Lo Wu Station
25,400 h,l
20
Lengthening of platforms, Kowloon, University, Fanling and
Sheung Shui Stations
100,000
21
Motor vehicle
19,200 fn
11,100
22
Overhead bridge and fence, Sha Tin
200,000
Public address system at Lo Wu
3,200
24
Renewal of permanent way
1,100,000
1,100,000
Renewal of signalling equipment, University and Tai Po Kau
500,000
26
Surfacing of station yards
60,000
27 Ticket machine
30,000
Calculating machine
3,500
Diesel electric locomotive
450,000
Waiting shelter and re-surfacing, Tai Po Market
Improvements to lighting, Sha Tin, Tai Po Kau and Tai Po
Market
Public address systems, Sha Tin and Sheung Shui
Waiting shelter, Tai Po Kau
10,300
5,500
115,000
65,000
Widening of embankment (Stage II)
83,000
Total, Special Expenditure
2,532,900
2,420,400
Total, Other Charges
5,072,600
4,342,500
Total Expenditure
9,632,800
8,234,000
Subhead 21 Replacement.