Pro- gramme No.
Head 63-PUBLIC WORKS NON-RECURRENT: WATERWORKS
Estimated Expendi- ture to 31st March
Estimate 1967-68
1
175
Estimate
Revised Estimate
Sub- head!
$
$
1967
$
的
Hong Kong Island
1 Aberdeen Supply, Stage I
WH1
1,400,000
800,000
2 Central City Distribution System
WH2
27,600
10,000
3 Chai Wan Distribution System
WH3
1,000,000
295,000
100,000
4 Chung Hom Kok Fresh Water Supply WH4
200,000
90,000
20,000
5 Conduit Road Service Reservoir
WH5
1,996,000
1,983,000
13,000
6 Eastern Extension Service Reservoir. WH6
9,000,000
2,692,000
3,340,000
7 Improved Supplies to Mount
Cameron and Magazine Gap, Stage II
WH11
1,260,000
1,202,000
58,000
8 Pok Fu Lam Supply:
(1) Stage I (Queen Mary Hospital). WH14 (2) Stage II
2,400,000
1,844,000
150,000
WH15
3,500,000
2,369,000
358,000
9 Shau Kei Wan Service Reservoir
WH16
3,900,000
2,000,000
10 Stanley and Repulse Bay Supply,
Stage II
WH17
4,250,000
10,000
1,900,000
11 Pumping Main to Victoria Peak
WH19
800,000
1,000
799,000
12 Additional Salt Water Flushing
Supplies at Aberdeen
WH21
760,000
518,000
122,000
13 Central District Salt Water Flushing
System, Stage I
WH22
1,300,000
570,000
14 Salt Water Flushing Systems:
(1) Chung Hom Kok
WH24
400,000
22,000
10,000
(2) Kennedy Town
WH25
700,000
473,000
227,000
(3) North Point
WH26
1,600,000
1,120,000
100,000
15 | Additional Staff Quarters and Chemists
Laboratory at Eastern Filters and
Pumping Station, Stubbs Road
WH28
450,000
35,000
385,000
16 Reprovisioning of Blake Pier and
Rumsey Street Salt Water Pump Houses
WH34
200,000
55,000
145,000
17 Jardine's Lookout and Tai Hang
Areas, Improved Supplies, Stage I. WH35
2,350,000
500,000
11,607,000
Kowloon and New Kowloon
18 Supply to Rennie's Mill
WN47
650,000
583,000
20,000
19 Beacon Hill Service Reservoir and
Pumping Station
WKI
3,620,000
2,471,000
694,000
20 Trunk Main across Cheung Sha Wan
Reclamation
WK2
600,000
504,500
95,000
21 Ham Tin Service Reservoir
WK4
4,800,000
4,297,000
200,000
22 Ho Man Tin Development Supply,
Stage II
WK5
6,500,000
3,748,000
348,000
23 Kowloon East Salt Water System
(Mains)
WK7
1,600,000
1,488,000
86,000
24 Kwun Tong New Town Supply:
Housing Zones 13 and 14
WK13
470,000
233,100
10,000
25 Yau Tong Supply:
(1) Stage II (Extension of Trunk
Feed and Construction of Fresh
Water Service Reservoir)
WK18
3,750,000
3,089,400
4,000
(2) Stage III (Construction of Salt
Water Pump House and Reservoir)
WK 19
1,823,000
846,500 861,000
26 Salt Water Flushing Systems:
(1) Kwun Tong
WK22
3,350,000
3,320,000
10,000
(2) Wong Tai Sin (Kai Tak) (3) Kwun Tong--Jordan Valley
WK23 4,700,000
4,553,000
100,000
WK25
3,250,000
628,000
2,622,000
27 Kowloon East Salt Water System
(Pumping Station and Additional
Mains)
WK24
3,650,000
1,336,000
28 Trunk Supply Mains:
Kowloon East
WK28
4,600,000
1,945,000
2,034,000 2,000,000
29 Ham Tin Fresh Water High Level
Supply
WK29
4,000,000
20,000
30 Salt Water Flushing System, Sau Mau'
Ping
WK30
2,400,000
730,000
31 Kowloon Bay Reclamation Section
A, Supply
WK31
670,000
10,000
9,755,000