Head 62-PUBLIC WORKS NON-RECURRENT: CIVIL ENGINEERING 169
Pro-
gramme Estimate
Revised Estimate
Estimated Expendi-
Estimate
No.
ture to 31st March
1967-68
$
1967
$
Sub- head
Hong Kong Island—Contd.
Port Works and Development
44 Incineration Plant, Hong Kong Island HP1 45 Aberdeen Reclamation Model
19,000,000 21,000,000 | 19,675,000
1,200,000
HP2
150,000
146,000
1,000
46 Aberdeen Reclamation and Typhoon
Shelter, Stage I
HP3
8,000,000
7,142,000
15,000
47 Central Reclamation, Stages II
and IV
HPS
19,700,000
17,079,000
630,000
48 Chai Wan Seawall, Stage I
HP6
8,000,000
1,209,000
1,000
49 Kennedy Town Reclamation
HP7
1,200,000
567,000
10,000
50 Sandy Bay Reclamation, Stage II
HP9
5,700,000
2,815,000
270,000
51 Marine Police Pier and Access Road,
Aberdeen
HP10
1,000,000
693,000
60,000
52 Vehicular Ferry Piers (North Point/
Kowloon City)
HP14
5,900,000
5,707,700
1,000
53 Wan Chai Cargo Handling Basin,
Breakwater Arm
HP19
4,000,000
1,200,000
54 Wan Chai Reclamation, Stage I 55 Aberdeen Southern Breakwaters
HP21
24,500,000
5,074,000
4,300,000
HP22
14,000,000
4,750,000
2,200,000
9,888,000
Kowloon and New Kowloon
Roads and Bridges
56 Cheung Sha Wan Road Extension and
Partial Reconstruction
KR5
2,500,000
1,000,000
57 Choi Hung Road Improvements
KR6
2,560,000
1,624,000
535,000
58 Extension of Aircraft Parking Apron,
Kai Tak
KR11
4,690,000
500,000
1,880,000
59 Kwun Tong Road:
(1) Stage I
KR12
3,800,000
3,662,000
5,000
(2) Stage IV
KR13
1,800,000
1,218,000
100,000
60 Kwun Tong New Town, Roads and
Drainage for:
(1) Housing Zones I, II and III and
Commercial Centre
KR14
5,800,000
5,213,000!
200,000
(2) Industrial Zone 5, Section A
KR15
5,180,000
4,705,000
80,000
(3) Industrial Zone 5, Section B
KR16
2,600,000
2,154,000
140,000
(4) Industrial Zone 6
KR17
1,750,000
1,575,000
80,000
61 Lai Chi Kok Road Extension (Ton
Kin Street to Kom Tsuen Street)
KR19
3,850,000
1,825,000
140,000
62 Lai Chi Kok Road/Nathan Road
Junction Improvements
KR20
700,000
550,000
20,000
63 Lung Cheung Road Extension,
Stage I
KR21
1,200,000
315,000
310,000
64 Reconstruction of Nathan Road
(Chang Sha Street to Arran Street) KR27
1,200,000
1,176,000
20,000
65 Sha Tin Pass Road Reconstruction KR28 66 Sha Tin Tunnel Approach Road- South Portal to Lung Cheung Road
1,280,000
1,228,000
50,000
KR29
1,850,000
1,276,000
30,000
67 Tai Po/Castle Peak Road Link 68 Road from Tsim Sha Tsui to Airport: Chatham Road/Ma Tau Wai Road Junction Improve- ments, Stage I (Signals Scheme) ... KR32
KR30
4,412,000 4,926,000
4,902,000
24,000
550,000
547,000
3,000
69 Road from Tsim Sha Tsui to
Airport: Widening of Chatham
Road (Salisbury Road to Gascoigne Road)
KR34
1,350,000
804,000
10,000
70 Road from Tsim Sha Tsui to
Airport: Widening of Chatham
Road (Winslow Street to Ma Tau Wai Road)
KR35
420,000
6,900
350,000
71 Waterloo Road, Extension to
Lung Cheung Road
KR38
1,000,000
844,000
5,000
72 Reconstruction of Waterloo Road
(Boundary Street to approach ramp of Flyover at Nairn House Inter- section)
KR39
520,000
430,000
60,000
Page 175Page 176