Estimates 財政預算 All

No.

Appendix VI-Contd.

Project

A

B

C

PORT WORKS

ΡΚΙ

Incineration and Composting Plant, Kowloon

63/SEP

61/3

PK2

Cheung Sha Wan Reclamation, Stage II

58/3

PK3

Cheung Sha Wan Reclamation, Landing Stages

59/2

58/3

PK4

Hung Hom Reclamation, Stages IIB and IIA and main drainage

62/2

61/2

60/1

*PK5

To Kwa Wan Reclamation

61/3

60/1

*PK6

Yau Ma Tei Typhoon Shelter, Improvements

58/1

PK7

Cha Kwo Ling Seawall, Stage I

64/2

63/3

60/1

PK8 PK9 *PK 10 PK11

Cha Kwo Ling Seawall, Stage II

64/3

64/2

63/3

Tai Wan Seawall

64/2

60/1

Temporary Vehicular Ferry Pier, Jordan Road

63/MAR

To Kwa Wan Public Pier

60/1

PK12

PK13

Kwun Tong/North Point Combined Vehicular and Passenger Ferry Piers Yau Ma Tei Slipway Reprovisioning, Stage I (Pier and Slipway)

63/3

63/2

62/3

59/3

*PK15

Temporary Sand Depot, Kwun Tong

64/1

PK16

Second Incinerator in Kowloon

65/3

64/2

PK18

PK19

PK20

Extension of Jordan Road Seawall and Reclamation

Reclamation for Tong Mi Road Extension

Kowloon Bay Seawall Part II

* Completed Items

DEVELOPMENT

DEK1 Ho Man Tin Development, Stages I to IV

64/3

64/3

65/3

62/1

DEK2 Ho Man Tin Development, Stages VI and VIII

63/3

62/1

DEK3 Ho Man Tin Development, Stage VII

62/1

DEK4 Ho Man Tin Development, Stage X

64/1

63/1

DEK5 Kai Tak Airport Development (Consulting Engineers)

54/OCT

DEK6 Kowloon Bay Reclamation, Investigation

62/3

DEK7 Kwun Tong New Town, Site Formation and Associated Works

61/1

58/3

*DEK8 Kwun Tong Road Reclamation

60/1

DEK9 Lung Cheung Road Development Area I

64/1

61/2

DEK 10 Lung Cheung Road Development, Area 3, Stage I

62/1

61/2

DEK11 Lung Cheung Road Development Area 3, Stage II

62/3

61/2

DEK 12 Shun Lee Tsuen Development, Clear Water Bay Road

62/3

DEK13 Sam Ka Tsuen Development Stages I to III

63/3

63/1

61/3

DEK 14 Waterloo Road Hill Development, Stage II

61/3

61/1

DEK 15 Yau Tong East Development

DEK 17 Resiting of Railway Terminus

63/3

63/2

DEK 16 Service Hospital, King's Park, Ancillary Works

63/3

63/MAY

DEK 18 Wing Hong Street Exchange Area, Investigation

63/3

DEK 19 Kowloon Bay Reclamation, Preliminary Works

64/2

62/3

DEK 20 Kowloon Bay Reclamation, Stage I

64/2

62/3

DEK21 Construction of Railway Workshops and Ancillary Works

65/SEP

63/MAY

DEK22 Stormwater Culvert Extension at Cheung Sha Wan Reclamation DEK23 Resiting of the Railway Terminus, Preliminary Works

65/3

65/3

65/1 63/MAY

* Completed Items

No.

CIVIL ENGINEERING

NEW TERRITORIES

Project

А

B

C

ROADS AND BRIDGES

RN1

Lion Rock Tunnel

60/DEC

RN2

Road through Lion Rock Tunnel

64/1

62/FEB

RN3

Sha Tin Tunnel Approach Road-North Portal to Sha Tin

63/3

62/1

RN4

Castle Peak Road, Dual Carriageway, Stage II (Lai Chi Kok Gap to

Motion Picture Studio)

61/3

59/3

RN5

Castle Peak Road Improvements (Chai Wan Kok)

60/1

RN6

Castle Peak Road, Dual Carriageway (Tsuen Wan to Castle Peak)

65/1

59/3

RN7 Bridge at 231 M.S., Castle Peak Road

62/1

58/3

RN8

Hang Hau Road, Junk Bay

61/3

59/3

RN9

Hok Tau Valley Road, Tai Po

63/3

RN10

RN11

Castle Peak Road Improvements-Castle Peak to Ping Shan Kam Tin Road (through Kam Tin)

62/3

61/3

63/1

61/3

RN12

Kwun Tong/Ma Yau Tong/Junk Bay Road

61/3

60/3