Head 31-PUBLIC WORKS NON-RECURRENT
Estimated
105
Estimate
Revised Estimate
Expendi- Approved
ture to
Estimate
Roads and Bridges,—Contd.
31st March 1957-58
1957
Sub- head
Reconstruction
22
75
Tai Po Market Bridge
525,000
560,000
160,000
400,000
76
Castle Peak Road from Lai Chi Kok gap to
Tsuen Wan
4,412,000
5,072,000 4,741,460
330,540
77
Taipo Causeway alterations
480,000
780,000
780,000
78
Garden Road/Bowen Road junction
350,000 366,000 200,000
166,000
79
80
Eastern Hospital Road improvement Shek Wu Hui Scheme-roads and drainage
550,000
550,000
706,000
50,000
656,000
81
Other major motor roads and bridges
1,000,000 | e
3,882,540
Reclamations and Piers
91
******* 827
82
Star Ferry Piers
83
Hung Hom reclamation, Stage I
300,000
449,176
7,000,000 | 11,134,000 | 8,690,000 2,000,000
354,176 95,000
84
Hung Hom reclamation, Stage II
2,975,000
1,600,000
85
Cheung Sha Wan reclamation, Stage I
650,000
750,000
650,000 100,000
86
Chai Wan reclamation
525,000
2,415,000
245,000 1,000,000
87
Central reclamation, Stage III
3,600,000
3,820,000
69,000 | 1,750,000
88
Kennedy Town Abattoir, Stage I, completion of
sea wall, reclamation and provision of piers.
1,500,000
425,200
324,000
89
Tsuen Wan sea wall, Stage I....
1,000,000
800,000
90
Typhoon anchorage, Tsing Yi Island
350,000
300,000
Kun Tong reclamation, Stage III
15,000,000
100,000 | e
8,069,000
Drainage
92
Yaumati intercepting sewer and outfall
4,000,000
93
94
Eastern drainage scheme, Kowloon, Stage I Wanchai intercepting sewer and outfall
310,000 3,550,000
146,000 2,340,000 3,000,000 3,450,000 992,000
4,250,000 3,940,000
320,000
2,970,000
Water Supplies
95
96
Tai Lam Chung Scheme, Stages I, II & III... 125,000,000 134,000,000 83,000,000 24,000,000 Eastern and Albany Filters Conversion Scheme
and Tin Hau Temple Road supply
97
Tytam-Shaukiwan supply
98
Kowloon supply
4,000,000 4,950,000 2,370,000 | 2,000,000 2,700,000 3,300,000 3,207,000 93,000 2,100,000 3,100,000 2,270,000
830,000
99
New Reservoir, Lantau Island:
(a) Stage I, investigations
330,000 362,000 361,000
(b) Cut-off trench and grout curtain
15,000,000
1,000 1,000,000 e
100
Tsuen Wan supply.....
3,500,000
1,100,000 1,500,000
101
Western New Territories supply:
(a) Stage I
750,000
200,000
(b) Stage II....
5,500,000
550,000 1,000,000 e
102
Pumping plant.............
103
Deep Well Investigations, New Territories..
542,000 572,000 150,000
562,000 10,000
80,000 70,000
104
Kun Tong Development, Stages I and II and
Housing Zone No. 1
1,700,000
100,000 1,000,000
105
Fluoridation of supplies
280,000
280,000
32,334,000
Airport
106
Kai Tak Airport development...
96,750,000 104,500,000 47,510,000 38,200,000
38,200,000
Miscellaneous
107
Nullah-decking:
(a) Hill Road, West Point
265,000
265,000
(b) Nam Cheong Street, Shamshuipe
350,000
350,000
(c) Minor deckings and culverting
100,000
100,000