Estimates 財政預算 All

80

HONGKONG ESTIMATES

PUBLIC WORKS.

Original Revised

PUBLIC WORKS,—Continued.

Estimate.

Estimate.

C.-PUBLIC WORKS, EXTRA-

ORDINARY,-Contd.

Brought forward,......

DRAINAGE, Continued.

80 Miscellaneous Drainage Works :—

(a.) Matauchung District, storm-

water drainage,

(b.) General Works,

MISCELLANEOUS.

81 Filling in Tidal Flat and cutting down hill between Taikoktsui and Fuk Tsun Heung,

82 Kowloon Bay West Reclamation, 1st Section Area between New Re- clamation line and Kowloon City Road and between San Shan and the proposed 100 foot road con- taining the Matauchung Nullab, ... 83 Furniture for Government Offices

and Quarters,

$

Estimated Expenditure during 1922.

Estimated

Total Expen-Estimated

diture to 31st Dec.,

1922.

Expenditure,

1923.

5,581,500

******

...

10,000

10,000

30,000 30,000

326,000

60,000

95,000

60,000

20,000

10,000

8,000

10,000

84

85

Two 2-ton Lorries for Kowloon Roads, Chinese Cemeteries,-Laying out new

8,000

16,000

2,000

5,000

8,000

areas,

86 Kowloon, King's Park, Laying-out

Ground for Recreation purposes.

20,000

5,000

11,000

10,000

87 Miscellaneous Works,

PUBLIC HEALTH AND BUILDINGS ORDINANCE, 1903.

88 Compensation and Resumptions,

30,000

15,000

30,000

WATER WORKS.

89 Enlarging mains to improve the dis-

tribution system in Kowloon,

90 Miscellaneous Water Works,

NEW TERRITORIES.

25,000

25,000

15,000

8,000

8,000

8,000

BUILDINGS.

91 Gaol, Ngau Shi Wan,

..

92

New Police Station, Shatin,..

35,000

50,000 35,000

......

50,000

15,000

20,000

93 Quarters for Indian Married Police,...

3,200

8,000

(per block)

94 Quarters for Government Officers,

North of Kaulungtong area,

10,000

95

Land Court Building, Taipo, addition

of Survey Offices,

14,200

10,000

96

Erection of a brick Bungalow at Tai

Po for Public Works Department

in place of the existing one,

35,000

20,000

20,000

97 Reconstruction of certain sheds at

Laichikok,

G

20,000

26,000

26,000

98 Quarters for Inspector of Vernacular

99

Education in the New Territories, Taipo, Block House for Police, Castle Peak, 100 Public Latrines and Urinals,............

15,000

35,000

15,000

5,000

30,000

11,000

4

11,000

5,000

6,000

15,000

15,000

101 Roads :-

COMMUNICATIONS.

(a.) Metalling and tar-painting hilly portion of Lai Chi Kok-

Castle Peak and Taipo Roads,.

70,000

70,000

70,000

(b.) Taipo to Shun Wan Road,

13,000

20,000

13,000

13,000

7,000

(c.) Patrol Path,-Sheung Shui to

Frontier,

14,000

22,000

12,000

(d) Taipo Market, kerbing and

12,000

10,000

channelling, &c.,................

11,000

11,000

5,000

(e.) Taipo Road,-Widening and

improving from 5th milestone to Shatin,

30,000

10,000

10,000

20,000

Carried forward,..

6,145,500