XN000022-1997-04-09 — Page 60

Daily Information Bulletin 新聞公報 All

End

43

Progress of Works or Studies

Expected Date of Works Completion

No.

Name of School

work completed,

11.

*The Building Contractors'

AP appointed.

Note 2

Association School

Tendering procedures for

proposed ground investigation

work completed.

12.

*The True Light Middle School

of Kowloon

AP appointed.

Note 2

Tendering for ground

investigation works in progress.

13.

Raimondi College

AP appointed.

Note 2

Ground investigation proposal

approved

14,

SKH St. James' Primary School

AP appointment in progress.

Note 2

15.

Cognitio College

DH Order issued on 28.1.97.

end 97

Works already started.

16.

Marymount Secondary School

AP appointment in progress.

Note 2

17.

Caritas St. Paul Prevocational School Cheung Chau

Order served on 13.3.97. AP appointment in progress

Note 2

18.

Buddhist Chi Hong Kindergarten

Consent to commencement of works was issued.

Note 3

Note 1:

Note 2:

Note 3:

Apart from the 1st slope reported in June 1996, a separate DH Order has been issued in respect of a 2nd slope facing Kin Wah Street.

Date of completion depends on ground investigation which has not yet started or has not been completed.

Repair works will take approximately 4 months, however, commencement of works is subject to resolution of land status complications, since part of the proposed works extended outside lot of school

* School also reported in June 1996 list.