WEDNESDAY, JULY 8, 1992
ACP ESTIMATES EXPLAINED
*
THE ESTIMATED
COST OF THE
EXPRESSED IN MONEY OF THE DAY (MOD) IS $112,220 MILLION AT MARCH 1991 PRICES.
AIRPORT CORE PROGRAMME (ACP) $163,730 MILLION AS AGAINST
FOR THE TREASURY,
MR K.Y.
THIS WAS STATED BY THE SECRETARY YEUNG, IN A WRITTEN REPLY TO A QUESTION BY THE HON SAMUEL WONG, IN THE LEGISLATIVE COUNCIL TODAY (WEDNESDAY).
MR YEUNG SAID THE ESTIMATE AT MARCH 1991 PRICES AND THAT IN MOD APPLIED TO THE SAME SCOPE OF WORKS UNDER THE ACP AS WAS ANNOUNCED ON APRIL 2 THIS YEAR.
HE SAID EXPRESSING PROJECT ESTIMATES IN CONSTANT MARCH 1991 PRICES ENABLED REAL INCREASES IN COST TO BE READILY IDENTIFIED.
EXPRESSING PROJECT ESTIMATES IN MOD, ON THE
AN IDEA AS TO THEIR LIKELY OUTTURN, MR YEUNG SAID.
OTHER HAND,
GAVE
HE POINTED OUT THAT THE BASIS UPON WHICH MOD ESTIMATES FOR GOVERNMENT ACP PROJECTS WAS CALCULATED WAS EXPLAINED IN AN INFORMATION NOTE ENTITLED "GOVERNMENT EXPENDITURE ON THE AIRPORT CORE PROGRAMME: ADJUSTMENT FROM 1991 DOLLARS TO MONEY OF THE DAY" WHICH WAS ISSUED ON JUNE 3 THIS YEAR.
THE MOD EQUIVALENTS FOR THE OTHER ACP PROJECTS WERE RELEASED TO THE PUBLIC ON JUNE 12, HE ADDED.
A BREAKDOWN OF THE ACP ESTIMATED COST IS AS FOLLOWS:
ESTIMATE
ESTIMATE
PROJECT
AT MARCH 1991 PRICES
AT MOD PRICES
$ MILLION
$ MILLION
CHER LAP KOK AIRPORT
46,300
68,500
NORTH LANTAU EXPRESSWAY
5,790
8,102
TUNG CHUNG DEVELOPMENT PHASE I
2,210
3,027
LANTAU FIXED CROSSING
11,960
17,155
ROUTE 3 (PART)
6,050
8,918
WEST KOWLOON RECLAMATION
10,010
12,587
WEST KOWLOON EXPRESSWAY
2,230
3,383
WESTERN HARBOUR CROSSING
4.150
6,500