THE PLAN CAN ALSO BE SEEN AT THE BUILDINGS AND LANDS DEPARTMENT SURVEY AND MAPPING OFFICE, 14TH FLOOR, MURRAY BUILDING, GARDEN ROAD, HONG KONG (WHERE COPIES CAN BE PURCHASED ON ORDER); AT THE TSUEN WAN DISTRICT OFFICE, FIRST FLOOR, TSUEN WAN STATION MULTI-STOREY CARPARK BUILDING, 174-208 CASTLE PEAK ROAD, TSUEN WAN; AT THE KWAI CHUNG AND TSING YI PUBLIC ENQUIRY SERVICES CENTRE, KWAI TSING DISTRICT OFFICE, SECOND FLOOR, KWAI HING GOVERNMENT OFFICES BUILDING, 166-174 HING PONG ROAD, KWAI CHUNG; AND AT THE DISTRICT LANDS OFFICE, KWAI TSING, 10TH FLOOR, TSUEN WAN STATION MULTI-STOREY CARPARK BUILDING, 174-208 CASTLE PEAK ROAD, TSUEN WAN.
$120M CONTRACT FOR RECLAMATION AT MA ON SHAN SIGNED
A $120 MILLION CONTRACT
HAS BEEN AWARDED BY THE TERRITORY DEVELOPMENT DEPARTMENT (TDD) FOR THE RECLAMATION OF ABOUT 23 HECTARES OF LAND AT MA ON SHAN, SHA TIN,
THE CONTRACT WAS SIGNED TODAY (WEDNESDAY) BY THE MANAGER OF NORTH EAST NEW TERRITORIES DEVELOPMENT OFFICE BERNARD LAM, AND REPRESENTATIVES OF THE CONTRACTOR.
OF
PROJECT TDD, MR
IT IS THE LAST MAJOR RECLAMATION CONTRACT TO BE LET BY TDD AS PART OF THE CONTINUING PROGRAMME FOR THE DEVELOPMENT OF MA ON SHAN IN SHA TIN NEW TOWN.
THE PROJECT INVOLVES CIVIL ENGINEERING WORKS COMPRISING THE CONSTRUCTION OF A 1.1 KILOMETRE SEAWALL, RECLAMATION WORK AND ASSOCIATED STORMWATER DRAINAGE IN THE AREA NORTH OF ΤΑΙ SHUI HANG NULLAH IN MA ON SHAN.
WILL BE USED
FOR RESIDENTIAL,
THE LAND TO BE RECLAIMED INDUSTRIAL, GOVERNMENT/INSTITUTION AND COMMUNITY PURPOSES, AND DISTRICT OPEN SPACES AS PART OF THE DEVELOPMENT PROGRAMME FOR THE SHA TIN NEW TOWN.
THE PROJECT WILL ALSO INCLUDE THE PROVISION OF A STRATEGIC PUBLIC DUMPING SITE, CAPABLE OF ACCOMMODATING 1.5 MILLION CUBIC METRES OF DUMPING MATERIALS IN THE AREA.
WORK IS EXPECTED TO COMMENCE AFTER THE LUNAR NEW YEAR AND WILL TAKE ABOUT 27 MONTHS TO COMPLETE.