SATURDAY, FEBRUARY 25, 1989
CONSTRUCTION OF THE MAIN HOSPITAL COMPLEX, WHICH WILL ESTIMATED $2 BILLION, STARTED LAST AUGUST.
COST AN
THE COMPLEX WILL INCLUDE A 14-STOREY MAIN BLOCK, A 12-STOREY SPECIAL BLOCK, A NINE-STOREY PATHOLOGY BLOCK, A SIX-STOREY POLYCLINIC
THREE-STOREY BLOCK, A
NURSES TRAINING SCHOOL AND STAFF QUARTERS RANGING FROM 12 TO 22 STOREYS.
THE BUILDINGS WILL BE LINKED BY TUNNELS, DECKS AND FOOTBRIDGES.
BE CUT ALSO
THE 10-HECTARE HOSPITAL SITE ON THE SLOPE HAS
AND BACK TO FORM SEVERAL TERRACES
AIRPORT RADAR RESTRICT THE HEIGHT OF THE BUILDINGS.
ΤΟ HAD REQUIREMENTS
SITE REQUIRED
THE
OF CONSTRUCTION
A
THE TOPOGRAPHY OF THE SECOND INGRESS ROAD DIRECT FROM THE ISLAND EASTERN CORRIDOR.
SERVICES TERMINATE
PROVISIONS WILL TO FURTHER FACILITATE ACCESS TO THE HOSPITAL,
MINIBUS NETWORK FOR BE MADE ON THE INTERNAL ELEVATED ROAD
AND FROM CHAI WAN AND SHAU KEI WAN TO
THE COMPLEX TOGETHER WITH TAXIS AT THE HOSPITAL MAIN ENTRANCE.
ENTER
CHAI WAN WILL PROVIDE
THIS IS IN ADDITION TO THE PUBLIC BUS SERVICES ALONG ROAD AND THE MASS TRANSIT RAILWAY SYSTEM, BOTH OF WHICH CONVENIENT SERVICE TO THE HOSPITAL.
AT THE PEAK OF CONSTRUCTION SO FAR, 120 LORRY-LOADS OF CONCRETE WERE USED EACH DAY, AND THE DAILY WORKFORCE NUMBERED AROUND 1,200.
KW 30,000
DAILY TO SUFFICIENT FOR A SMALL
THE HOSPITAL IS EXPECTED TO REQUIRE SOME MEET ITS ELECTRICITY REQUIREMENTS, WHICH IS TOWN OF 30,000 PEOPLE.
NOTE TO EDITORS:
TO
FOUNDATION STONE THE GOVERNOR, SIR DAVID WILSON, WILL LAY THE OF THE PAMELA YOUDE HOSPITAL AT A CEREMONY TO BE HELD FROM 2.30 PM 3.30 PM ON MONDAY (FEBRUARY 27).
TO FACILITATE PRESS COVERAGE OF THE EVENT, A COACH THE CGO CARPARK AT 1.15 PM FOR THE HOSPITAL SITE.
WILL LEAVE