SHAU KEI WAN MAIN STREET EAST TO BE WIDENED
*
AND THE FLOODING
ALONG SHAU KRI WAN MAIN PROBLEM IN THE AREA SOLVED UPON PROGRAMME WHICH BEGAN YESTERDAY
VEHICULAR TRAFFIC WILL BE IMPROVED
EAST STREET COMPLETION OF A (WEDNESDAY).
ROAD IMPROVEMENT
UNDER THE $2.5 MILLION PROJECT, WHICH WAS DESIGNED AND WILL BR SUPERVISED BY THE HIGHWAYS DEPARTMENT, A SECTION OF SHAU KEI WAN STREET EAST BETWEEN THE JUNCTIONS OF KAM WA AND MIU TUNG STREETS BE WIDENED TO 7.3 METRES.
MAIN WILL
THE PROJECT ALSO INCLUDES RAISING THE LEVEL OF THE EXISTING ROAD AND LAYING NEW STORMWATER DRAINS AND A SEWERAGE SYSTEM TO REMOVE
PROJECT THE PROBLEM OF PERSISTENT FLOODING,
ENGINEER, MR K.C. CHAN
SAID.
MR CHAN SAID THE 250-METRE SECTION OF THE ROAD, NOW COVERED WITH BITUMINOUS MATERIAL, WOULD BE PAVED OVER WITH CONCRETE.
THE CONTRACT FOR THE PROJECT
HAS BEEN AWARDED ΤΟ WING MOU CONSTRUCTION COMPANY LIMITED. IT WILL TAKE 20 MONTHS TO COMPLETE.