XN000022-1987-04-12 — Page 11

Daily Information Bulletin 新聞公報 All

SUNDAY, APRIL 12, 1987

10

MOVE TO IMPROVE WATER SUPPLY TO YUEN LONG

****

TENDERS ARE INVITED BY THE WATER SUPPLIES DEPARTMENT FOR ABOUT 2 500 METRES OF WATER MAINS TO BE LAID ALONG CASTLE PEAK ROAD, FROM TAN KWAI TSUEN NEAR HUNG SHUI KIU TO YUEN LONG.

THE NEW 700-MILLIMETRE DIAMETER WATER MAINS, A DUPLICATE OF EXISTING MAINS ALONG CASTLE PEAK ROAD, IS REQUIRED TO COPE WITH INCREASING DEMAND IN THAT SECTION OF ROAD AND YUEN LONG NEW TOWN.

WORK IS EXPECTED TO START IN JUNE AND WILL TAKE 10 MONTHS TO COMPLETE.