THE CONSULTANCY WOULD SPECIFICALLY CONDUCT STUDIES ON VARIOUS ASPECTS INCLUDING PROVISION OF POTABLE AND IRRIGATION WATER SUPPLY FOR THE SURROUNDING VILLAGES, PROVISION OF ROAD ACCESS TO THE LANDFILL AND THE SURROUNDING VILLAGE AREAS, ALL NECESSARY CONTROLS NEEDED TO REDUCE NUISANCE ARISING FROM DUST, ODOUR, GAS, AND NOISE FROM LANDFILL OPERATIONS AND THE DEVELOPMENT NEEDS OF THE TA KWU LING AREA BY THE PROVISION OF A RURAL SERVICE CENTRE AND SEWERAGE AND SEWAGE TREATMENT FACILITIES.

IN DEVELOPING PROPOSALS FOR THE LANDFILL SITE, PARTICULAR ATTENTION WILL BE GIVEN TO THE LANDSCAPING REQUIREMENTS SO THAT PROGRESSIVE RESTORATION OF THE SITE IS ACHIEVED THUS ALLOWING A SWIFT RETURN TO ITS FINAL LAND USE PROBABLY FOR RECREATIONAL PURPOSES.

THE SITE INVESTIGATIONS AND THE ENVIRONMENTAL IMPACT ASSESSMENT STUDY WOULD BE COMPLETED BY OCTOBER THIS YEAR SO THAT THE PROPOSED LANDFILL COULD BE COMMISSIONED IN TIME TO REPLACE THE EXISTING NORTHEAST NEW TERRITORIES FACILITY AT SHUEN WAN BY EARLY 1990.

THE COST OF THE CONSULTANCY WITH RELATED SITE INVESTIGATIONS IS $8 MILLION.

CLOSURE OF KWAI CHUNG ILLEGAL STRUCTURES

*****

THE BUILDING AUTHORITY IS SEEKING CLOSURE OF A NUMBER OF ILLEGAL STRUCTURES ON THE FLAT ROOF ADJACENT TO FLAT F ON THE FIRST FLOOR OF 33-57 TAI PAK TIN STREET, KWAI CHUNG, SO THAT THEY CAN BE DEMOLISHED.

THIS FOLLOWS THE OWNERS' FAILURE TO COMPLY WITH ORDERS ISSUED UNDER THE BUILDINGS ORDINANCE IN JUNE 1985, REQUIRING DEMOLITION OF THE STRUCTURES.

A NOTICE OF INTENTION TO APPLY FOR A CLOSURE ORDER IN TSUEN WAN DISTRICT COURT ON APRIL 29, WAS POSTED ON THE STRUCTURES TODAY (MONDAY).

DEMOLITION WORK WILL BE CARRIED OUT IMMEDIATELY AFTER THE CLOSURE ORDER IS OBTAINED.