CHEUNG CHAU FERRY PIER BEING EXTENDED

*****

WORK HAS STARTED ON EXTEND ING CHEUNG CHAU FERRY PIER TO INCREASE PASSENGER FLOW.

THE EXTENSION WILL BE BUILT ALONGSIDE THE EXISTING PIER WHICH WILL ALSO BE MODIFIED. IT WILL INCREASE THE PASSENGER WAITING AREA AND ENABLE THE INSTALLATION OF A LIFT AND RAMPS.

AN $8.6 MILLION CONTRACT FOR THE EXTENSION HAS BEEN AWARDED TO HOI SING CONSTRUCTION COMPANY LIMITED WHO WILL TAKE 18 MONTHS TO COMPLETE THE PROJECT.

THE WORK HAS BEEN DESIGNED AND WILL BE SUPERVISED BY THE PORT WORKS DIVISION OF THE CIVIL ENGINEERING SERVICES DEPARTMENT.