XN000022-1985-04-16 — Page 12

Daily Information Bulletin 新聞公報 All

iusab.

++

AP-IL 1, 1985

11

PICNIC PRIZE FOR SCHEME WINNERS

* *

TWO HUNDRED AND FIFTY WINNERS OF THE +1984-85 CLEAN AND GREEN SCHEME+ WILL BE ENTITLED TO A FREE PICNIC AT CHEUNG SHEUNG IN SAI KUNG ON APRIL 28.

1

THE WINNERS WERE DRAWN FROM AMONG 732 PERSONS WHO HAD SUCCESSFULLY COMPLETED STAGE AND I OF THE SCHEME, AT A LUCKY DRAW HELD AT THE GOVERNMENT INFORMATION SERVICES PROMOTIONS SUB-DIVISION TODAY.

J

STAGE 1 OF THE SCHEME INVOLVED LITTER-PICKING IN 12 DESIGNATED COUNTRY PARKS BETWEEN DECEMBER LAST YEAR AND FEBRUARY THIS YEAR WHILE STAGE 11, WHICH ENDED LAST SUNDAY, INVOLVED PLANTING A TREE IN ANOTHER SIX DESIGNATED COUNTRY PARKS.

THE WINNERS WILL BE INFORMED OF THE DETAILS BY POST.

SPEAKING AT THE LUCKY DRAW, THE CHAIRMAN OF THE CLEAN AND GREEN SCHEME WORKING GROUP, MR HOWARD YOUNG, SAID THAT TAKING INTO ACCOUNT THE WET WEATHER DURING THE PAST FEW WEEKS, HE WAS QUITE PLEASED WITH THE NUMBER OF PERSONS WHO TOOK PARTÍCIPATE IN THE SCHEME.

+FOR THOSE WHO WERE NOT CHOSEN IN THE LUCKY DRAW, WE WOULD LIKE TO THANK THEM FOR THEIR SUPPORT AND HOPE THEY WILL CONTINUE TO TAKE PART IN THE SCHEME IN FUTURE,+ HE SAID.

WORK STARTS ON SCREENING PLANT

****

WORK HAS STARTED ON THE SHAM SHUI PO SCREENING PLANT, TO IMPROVE THE WATER QUALITY IN THE NORTH-WESTERN SECTION OF VICTORIA HARBOUR.

A $13.5 MILLION CONTRACT FOR THE JOB WAS RECENTLY AWARDED BY THE ENGINEERING DEVELOPMENT DEPARTMENT.

THE SCREENING PLANT, LOCATED IN YEN CHOW STREET, IS THE FIRST PHASE OF THE NORTH WEST KOWLOON SEWAGE TREATMENT AND DI SPOSAL PROJECT.

CONSTRUCTION WORK IS EXPECTED TO BE COMPLETED IN 19 MONTHS.