THURSDAY, JULY 26, 1984
14
CATERING EQUIPMENT FOR POLICE STATION
III
CATERING EQUIPMENT VALUED AT ABOUT $93 000 IS TO BE INSTALLED AT MONGKOK POLICE STATION.
THE BUILDING DEVELOPMENT DEPARTMENT HAS AWARDED A CONTRACT FOR THIS SUM TO THE HONG KONG AND CHINA GAS COMPANY LTD.
THE 10-STOREY BUILDING AT THE JUNCTION OF NATHAN ROAD AND PRINCE EDWARD ROAD WEST IS NOW BEING MODERNISED.
THE WORK INCLUDES PARTITIONING, INSTALLING NEW TOILETS, RENOVATING AND MODERNISING THE CANTÉEN AND KITCHEN AND REFURBISHING THE INTERIOR.
WORK IS EXPECTED TO BE COMPLETED BY THE END OF THE YEAR.
STORMWATER DRAINS FOR QUARRY BAY
***
THE GOVERNMENT IS TO SPEND $5.09 MILLION ON EXTENDING THE STORMWATER DRAINS AT QUARRY BAY AS A RESULT OF RECLAMATION.
THEY WILL RUN FROM THE OLD SEAWALL TO THE NEW ONE CREATED BY THE RECLAMATION.
A WORKS CONTRACT HAS BEEN AWARDED TO HANG KEE CONSTRUCTION COMPANY BY THE CIVIL ENGINEERING OFFICE OF THE ENGINEERING DEVELOPMENT DEPARTMENT.
THE PROJECT, WHICH WILL START EARLY NEXT MONTH, CALLS FOR LAYING 105 METRES OF BOX CULVERT AND 370 METRES OF PRECAST CONCRETE PIPES.
WHEN THE NEW STORMWATER DRAINS ARE READY BY THE END OF 1985, THE EXISTING TEMPORARY CHANNELS WILL BE COVERED TO IMPROVE THE ENVIRONMENT.
TRAFFIC MEASURES IN ABERDEEN
***
FROM 10 AM ON SATURDAY (JULY 28), THE SECTION OF TUNG SING ROAD BETWEEN WU PAK STREET AND WU NAM STREET AND THE SECTION OF WU NAM STREET BETWEEN TUNG SING ROAD AND ABERDEEN MAIN ROAD WILL BE CLOSED TO TRAFFIC FOR ABOUT THREE WEEKS TO FACILITATE ROAD CONSTRUCTION WORKS.
DURING THE CLOSURE, TRAFFIC ON CHENGTU ROAD SOUTHBOUND HEADING FOR ABERDEEN MAIN ROAD EASTBOUND WILL BE DIVERTED VIA NAM NING STREET AND FUNG TIN STREET.
+
BUSES ON ROUTES 70 AND 72 AND MAXICABS ON ROUTES 4, 5, 27 AND 35 FROM ABERDEEN TERMINI WILL BE DIVERTED VIA TUNG SING ROAD TO REJOIN ABERDEEN MAIN ROAD.