CONTRACT FOR WATERWORKS IMPROVEMENT

*****

THE WATER SUPPLIES DEPARTMENT WILL BUILD A NEW SERVICE RESERVOIR TO MEET GROWING DEMAND FOR WATER SUPPLY IN WONG CHUK HANG AND THE LOW LEVEL AREA OF SHOUSON HILL.

A CONTRACT FOR THE PROJECT HAS BEEN SIGNED BY THE CHIEF ENGINEER (CONSTRUCTION) OF THE DEPARTMENT, MR LEE GUN-CHEUNG, WITH A REPRESENTATIVE OF GAMMON (HONG KONG) LTD.

THE SERVICE RESERVOIR, AT A COST OF $11 MILLION, WILL BE LOCATED SOUTH OF WONG CHUK HANG ESTATE AND WILL HAVE A TOTAL

IT WILL BE REACHED BY STORAGE CAPACITY OF 15 200 CUBIC METRES.

A ROAD TO BE BUILT UNDER THE SAME CONTRACT.

WORK WILL START LATER THIS WEEK AND WILL TAKE 18 MONTHS.

THE RESERVOIR IS PART OF THE NEW WONG CHUK HANG AND SHOUSON

HILL FRESH WATER SUPPLY SYSTEM.

A PUMPING STATION WILL ALSO BE BUILT AND TRUNK AND DISTRIBUT JON MAINS WILL BE LAID FOR THE SYSTEM.

WONG TAI SIN WATER CUT

***

WATER SUPPLY TO AN AREA OF WONG TAI SIN WILL BE INTERRUPTED FROM 10 PM ON FRIDAY (NOVEMBER 28), TO 6 AM THE FOLLOWING MORNING.

WAN

THE AREA COVERS PREMISES ON WAN FUNG STREET, KAM FUNG STREET AND NGAN FUNG STREET,

: