THURSDAY, APRIL 10, 1980
5.
SERVICE RESERVOIR FOR NEW DEVELOPMENTS IN CHAI WAN
*****
RESIDENTS IN CHAI WAN WILL HAVE A NEW SERVICE RESERVOIR TO SUPPLY FRESH WATER TO THEM.
A CONTRACT FOR THE PROJECT WHICH COSTS NEARLY $16 MILLION WAS SIGNED THIS (THURSDAY) MORNING BETWEEN THE CHIEF ENGINEER
(CONSTRUCTION), MR LEE GUN-CHEUNG, OF THE WATER SUPPLIES DEPARTMENT AND REPRESENTATIVES OF LEIGHTON CONTRACTORS PTY LTD.
LOCATED AT CHAI WAN HILL, THE NEW RESERVOIR WILL HAVE A STORAGE CAPACITY OF 22 000 CUBIC METRÉS.
IT WILL BE CONSTRUCTED IN MASS CONCRETE AND WILL HAVE REINFORCED CONCRETE DECKING.
UPON COMPLETION IT WILL BE ABLE TO COPE WITH DEMAND FOR WATER FROM NEW DEVELOPMENTS IN THE AREA.
WORK ON THE PROJECTS WILL START NEXT WEEK AND WILL TAKE
18 MONTHS TO COMPLETE.
NIGHT CLOSURE OF PRINCESS MARGARET ROAD FLYOVER
*****
THE PRINCESS MARGARET ROAD FLYOVER WILL BE CLOSED BETWEEN 1 AM AND 6 AM ON MONDAY (APRIL 14) FOR RE-PAINTING OF ROAD MARKINGS.
DURING THE TEMPORARY CLOSURE, ALTERNATIVE GROUND LEVEL ROUTES WILL BE AVAILABLE FOR DIVERTED TRAFFIC AND APPROPRIATE TRAFFIC SIGNS WILL BE SET UP TO GUIDE MOTORISTS.