6

FOUNDATION WORK ON STUBBS ROAD FLYOVER MAKING HEADWAY

*****

CAISSON FOUNDATION WORK ON THE $54.6 MILLION STUBBS ROAD FLYOVER IS MAKING HEADWAY.

MR. YEUNG KIM-CHOY, CHIEF ENGINEER OF THE PUBLIC WORKS DEPARTMENT'S HIGHWAYS OFFICE, SAID THE PROJECT INVOLVES THE SINKING OF MORE THAN 170 PILĖS.

+SO FAR, NEARLY 100 OF THEM HAVE EITHER BEEN COMPLETED OR IN THE PROCESS OF CONSTRUCTION.+

IN THE MEANTIME, A CASTING YARD IS BEING SET UP NEAR THE SITE TO PRODUCE BEAMS FOR THE FLYOVER.

MR. YEUNG SAID THE FIRST COLUMN FOR THE ELEVATED ROAD WOULD GO UP WITHIN A MONTH.

ON COMPLETION IN THE SECOND HALF OF NEXT YEAR, THE 450-METRE LONG FLYOVER WILL LINK LOWER STUBBS ROAD WITH WONG NAI CHUNG GAP ROAD, THUS IMPROVING THE TRAFFIC FLOW AT THE STUBBS ROAD ROUNDABOUT.