SEWAGE TREATMENT PLANT SUBSTANTIALLY COMPLETE

******

WORK ON THE ADMINISTRATION BUILDING AND CONTROL ROOM OF THE DEEP WATER BAY REPULSE BAY SEWAGE TREATMENT AND DISPOSAL WORKS IS SUBSTANTIALLY COMPLETE.

A SPOKESMAN FOR THE CIVIL ENGINEERING OFFICE OF THE PUBLIC WORKS DEPARTMENT WHICH DESIGNS AND SUPERVISES CONSTRUCTION OF THE PROJECT SAID TODAY (MONDAY) THAT INSTALLATION OF ELECTRICAL WIRING AND MACHINERY IN THE CONTROL ROOM WOULD BEGIN SHORTLY.

THE $5.3 MILLION PROJECT IS EXPECTED TO BE COMMISSIONED IN AUGUST.

MEANWHILE, WORK ON THE AP LEI CHAU SEWAGE SCREENING PLANT STAGE I, INCLUDING THE ADMINISTRATION BUILDING AND STAFF QUARTERS, IS HALF COMPLETE WHILE MACHINERY HAS JUST BEEN ORDERED.

+ON COMPLETION IN AUTUMN NEXT YEAR SEWAGE FROM AP LEI CHAU PUBLIC HOUSING ESTATE PHASE I, NOW UNDER CONSTRUCTION, WILL BE TREATED BEFORE IT IS DISCHARGED VIA THE SUBMARINE OUTFALL INTO DEEPER WATER FOR ADEQUATE DILUTION AND SATISFACTORY DISPERSION,+ THE SPOKESMAN ADDED.