WORK ON PHASE 1 OF DENTAL TEACHING HOSPITAL

TO BEGIN SOON

***

THE SECOND PHASE OF THE CONSTRUCTION OF THE DENTAL TEACHING HOSPITAL ADJACENT TO TSAN YUK HOSPITAL IN SAI YING PUN WILL START SOON, THE PUBLIC WORKS DEPARTMENT ANNOUNCED TODAY (SATURDAY).

MR. C.C. TAM, PUBLIC WORKS DEPARTMENT'S SENIOR ARCHITECT IN CHARGE OF THE PROJECT SAID +WE HAVE ALREADY INVITED TENDERS FOR THE SECOND PHASE - THE CONSTRUCTION OF THE MAIN BUILDING AND HOPE TO AWARD THE CONTRACT BY THE END OF FEBRUARY.+

MEANWHILE WORK ON THE CLINIC IS PROGRESSING SATISFACTORILY. THE FIRST PHASE, INVOLVING THE CONSTRUCTION OF THE FOUNDATION AND SUBSTRUCTURE TO GROUND LEVEL, IS EXPECTED TO BE COMPLETED IN ABOUT TEN WEEKS.

THE 35,000 SQUARE-METRE CLINIC, WHEN COMPLETED BY THE END OF 1980, WILL PROVIDE DENTAL TEACHING FACILITIES FOR ABOUT 80 STUDENTS A YEAR. THE MEDICAL AND TEACHING AREAS OF THE CLINIC WILL BE AIR-CONDITIONED.