XN000022-1977-10-06 — Page 8

Daily Information Bulletin 新聞公報 All

Thursday, October 6, 1977

7

"A seawall 350 metres in length and a rubble wall me:suring

340 metres will be built to contain the filling," Mr. Keown said.

"Other infrastructure consists of 0.7 kilometre of two-lane

road and 1.8 kilometres of storm and foul water drains."

In the meantime, work has begun on the first stogo of the

development of Mui Wo, providing land for public and private housing.

About five hectares of land will be formed in this stage to

provide sites for a new and improved bus terminus, waterfront cooked

food stalls, public housing and commercial and light industrial use.

Also included in the stage one works are the construction of

1.1 kilometres of two-lane road and 2.7 kilometres of foul water drains.