Tuesday, October 23, 1973
Also included in the final phase of the project is the construction
of a single-storey modular market providing accommodation for some 30
stalls.
Stage I of the estate was completed last year and provides homes
for about 38,000 tenants in nine multi-storey blocks.
Work on Stage II is in full swing and it is envisaged to house
another 24,000 people. The final stage is due to commence in January next
year and should be completed in mid-1976.
NEW PLAYGROUND FOR POKFULAM
***
Residents of Pokfulam district on Hong Kong Island will have their
own public playground early next year.
The Urban Council has earmarked more than two acres of land to the
north-east of the junction of Mount Davis Road and Pokfulam Road for the new
playground.
There will be a miniature football pitch, two basketball and two
volleyball courts, and a playground with specially designed games equipment
for younger children.
A rest garden with a pavilion and the usual public toilet facilities
will also be provided.
All the games pitches will be floodlit at night while the garden and
the children's playground will have general park lighting.
Construction of the playground is expected to begin early in
December and take about five months to complete.
-