SHA TIN FLOOD CONTROL SCHEME ALMOST COMPLETE

The Shing Mun River flood control scheme in Sha Tin to protect

lowlying areas from flooding is nearing completion.

Work is expected to start later this year on the final stage of

the project. Those works have been designed to protect the areas adjacent

to the existing Tin San nullah in the small valley of the same name,

The nullah will be extended and part of its course, situated to

the north of Che Kung Temple on the south bank of the Shing Mun River, will

be reclaimed.

The course of the nullah will also be realigned and its banks lined

with concrete for about 1,000 feet to join the Shing Mun River.

The flood control scheme has been carried out progressively in

three stages. The overall plan was to deepen and wid:n the river to in-

crease its carrying capacity during periods of heavy rain, as well as to

straighten its course to facilitate water flow and to construct solid em-

bankments along the river connau,