XN000022-1973-06-29 — Page 10

Daily Information Bulletin 新聞公報 All

9

Friday, June 29, 1973

MAJOR FLYOVER FROJECT IN YAU MA TEI

Work on the first stage of the West Kowloon Corridor project

--

major scheme to distribute traffic in western Kowloon and provide a direct

link from the cross harbour tunnel to Kwai Chung and Tsuen Wan will begin

in August.

This first phase involves the construction of a section of a 4,200

foot-long flyover in Yau Ma Tei. -

This part of the flyover, measuring 2,200 feet long and 40 feet

wide, starts in Gascoigne Road near Wylie Road, It will run above Gascoigne

Road and across Nathan Road to terminate at the Yau Ma Tei multi-storey car park,

Construction for this section, costing about $20 million, is expected

to begin in about two months' time, and is scheduled for completion in two

years.

Tenders are now being invited for the work.

Caisson foundations will be used to eliminate noisy pile-driving

during construction,

This is done by sinking a large hollow tube into the ground by means

of excavating through the tube itself.

A heavy weight is then placed on top of the tube, forcing it down

further into the ground. This "dig and weight" process is continued until

solid rock is penetrated.

flyover.

Concrete is then poured into the tube to form the foundation for the

/The remaining