SHEK KIP MET REHOUSING PROJECT
Start of Phase Two
The second phase of the Shek Kip Mei rehousing project will start tomorrow (April 30). In the first phase which was completed on April 27, more than 11,000 domestic tenants and 44 shopkeepers were transferred to
Pak Tin Estate from 6 blocks (No. 23-28) in Shek Kip Mei Estate.
These blocks have now been handed over to P.W.D. and tenders for
carrying out conversion works will shortly be invited.
In the second phase, Block 3 and 4 are affected. Block 4 will be
converted into self-contained flats. Block 3 will be demolished to make way
for the construction of a road linking Berwick Street and Woh Chai Street to
improve traffic conditions for the future Shek Kip Mei Estate.
The 5,000 domestic tenants and 25 shopkeepers in these 2 blocks
will be transferred to Pak Tin Estate.
Workshop operators will be offered
temporary workshop spaces and will be eventually accommodated in the specially
built workshop block which is being built near Block 18 Shek Kip Mei Estate.
Re-provisioning arrangerents for business premises for the shopkeepers
will be on a 'foot-for-foot' basis similar to that offered to shopkeepers in the
first phase. The second phase is expected to be completed in four months,
We are
Mr. John Walden, Deputy Head of the Housing Department said:
extremely pleased with the way the first phase has gone. To assist almost
12,000 people to voluntarily move their homes and businesses from one place to
another without having to evict a single family is a pretty tough job.