ANOTHER LINK IN KOWLOON FOOTHILLS CORRIDOR

Work on another phase of the Kowloon Foothills Road Corridor

is expected to start next month.

This involves the extension of Lung Cheung Road from the

Po Kong Interchange, presently under construction, to its intersection

with Hammer Hill Road at the Choi Hung Estate.

It will be in the form of a new 2,000-foot-long three-lane

road with sewers and stormwater drains.

A temporary footbridge at Social Avenue will be built over

the new road so that easy access to Social Avenue for pedestrians can

be maintained.

Subject to the implementation and timing of the Mass Transit

Railway, an additional two lane temporary carriageway may also be provided.

If the railway is completed, additional traffic lanes will be

built and the final scheme will comprise a dual three-lane highway.

The present work, costing about $4.3 million, will take some 13 months

to complete.

The Kowloon Foothills Road Corridor is an important traffic route

which on completion will link Kwai Chung and Tsuen Wan in the west with

San Po Kong and Kwun Tong in the east and Sha Tin in the north, via the Lion

Rock Tunnel.

12

Issued by Government Information Services, Beaconsfield House, Hong Kong. Tel: 5-233191