INDOOR STADIUM TENDERS

Tenders are being invited for the construction of foundations for the

indoor stadium on the Hung Hom Reclamation.

Work will involve the construction of piling, caissons and caps for a large podium slab which will support the indoor stadium, and some

foundations for minor buildings in the complex.

I

The construction work is expected to start in October this year

and should be completed by November

. 1973.

The project has been designed, and gonstruction will be supervised.

by the Public Works Department.

The indoor stadium together with the surrounding podium, forms

Stage III Phase 3 of the multi-million dollar Hung Hom Development Scheme.

When completed, the stadium will have seating accommodation for

15,000 and will be used as a venue for sporting and public events.