XN000022-1972-05-15 — Page 17

Daily Information Bulletin 新聞公報 All

17

SURFACING OF SHUNG SHUN STREET

To Cope With Increased Traffic

Monday, May 15, 1972

The final surfacing of Shung Shun Street and Cha Kwo Ling Road

(from Shung Shun Street to Ko Chiu Road) is expected to start in July this

year.

The final surfacing is designed to cope with the increased volume

of vehicular traffic proceeding onto the newly developed sites of the Sam

Ka Tsuen area.

The work consists of laying five-and-a-half inches of bitumen

coated materials on the existing roads. The roads were originally constructed

with temporary surfacing materials, pending development of the area.

The work should take about five months to complete.

Relcase time: 7.30 p.m.

O

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.