Wednesday, May 10, 1972
The second footbridge is situated outside the Fire Brigade
Building, and the third to the east of Gilman Street near the International
Building.
"Streets (Alteration) Ordinance procedure for these footbridges
is being put in hand and assuming no objections are received work could commence towards the end of 1972 for completion by the end of 1973," he said.
In addition to these, he said, two further bridges are planned, one
crossing Pedder Street linking the General Post Office and Union House, and
the other one crossing the new road being built to the west of Connaught Road.
Bridges
"Both of these bridges will link up with the bridge being provided
by Hong Kong Lands and will be ready at the same time," he said.
Mr. Robson reiterated that the recent traffic measures to combat
increasing congestion in Central represented an interim stage for improvement to traffic generally as completion of the Connaught Road widening scheme
would provide a marked increase in road capacity.
"This should allow through traffic to have a much smoother passage
and syphon off a large proportion of the traffic now using Queen's and Des Voeux Roads Central. This in turn should improve the flow of traffic in the area, particularly in Des Voeux Road Central, to the benefit of public
transport using that route."
By that time, a review of stopping facilities for both franchised
buses and public light buses will have been undertaken, he added.
He repeated his recent warning that it might also being necessary
to place restrictions on kerb side activities at certain times of the day.