| Describe the Work, and where situated | Whether Constructing or under Repairs | Estimated Expenses | Authority under which it is executed | When Commenced | Whether Finished or Unfinished | Amount of Expenditure in Dollars |
|---|---|---|---|---|---|---|
| Additional Septic Tank at Repulse Bay | Construction | 15,000.00 | 19 | 20.7.33 | Finished | 5,869.79 |
| New Sewer—Wong Nei Chong Gap to Island Road in connection with the development of sites along this road | Do. | 27,000.00 | 20 | 17.5.33 | Finished | 27,000.00 |
| Chinese Cemeteries—laying out new areas | Do. | 6,000.00 | 21 | Annual Vote | ... | 5,821.77 |
| Colonial Cemetery—laying out new areas | Do. | 7,000.00 | 22 | Annual Vote | ... | 4,783.98 |
| Tsat Tsz Mui Quarry—Covering to mixing plants, new high tension cable and a Transformer House | Do. | 10,000.00 | 23 | 1.1.33 | Unfinished | 5,881.35 |
| Tsat Tsz Mui Quarry—Extensions and Improvements | Do. | 10,000.00 | 24 | ... | ... | ... |
| Re-wiring of Government Buildings | Do. | 25,000.00 | 25 | 1.1.33 | ... | 6,191.53 |
| Twelve E.H.T. Disconnecting Joint Boxes for Cable to Cape D'Aguilar | Do. | 5,700.00 | 26 | Not commenced | Unfinished | 3,726.51 |
| Laying telephone cable from the main route Victoria Gap—Bowen Hill | Do. | 7,000.00 | 27 | 19.10.33 | Finished | 5,128.92 |
| Laying telephone cable between G.P.O. and Cable Hut at Happy Valley | Do. | 42,000.00 | 28 | 21.9.33 | ... | 25,155.78 |
| Reinstatement of Government Retaining Walls | Repairs | 20,000.00 | 29 | 7.11.33 | Unfinished | 4,314.34 |
| Central Police Station—Extension to Store | Construction | 1,200.00 | 30 | January | Finished | 1,189.90 |
| Victoria Hospital—Tennis Court | Do. | 3,000.00 | 31 | March | ... | 2,345.96 |
| Victoria Hospital—Hot Water System to Maternity Block | Do. | 16,000.00 | 32 | Not Commenced | Unfinished | ... |
| Central Market—Fish Tanks | Do. | 2,000.00 | 33 | March | Finished | 1,992.60 |
| Traffic White Lines, Studs, etc. | Do. | 5,000.00 | 34 | Annual Vote | ... | 2,279.83 |
| Upper Peak Tram Station Parking Ground | Do. | 6,500.00 | 35 | 20.2.33 | Unfinished | 6,352.44 |
| Chai Wan Cemetery Sextons' Quarters | Do. | 2,500.00 | 36 | G.O. 781 of 33 September | ... | ... |
| Government Pavilion Gardeners' Quarters | Do. | 800.00 | 37 | Do. | ... | 703.32 |
| Botanical Gardens—Improvements | Do. | 6,600.00 | 38 | October | Finished | 2,901.38 |
| Extension to Building Ordinance Office | Do. | 11,000.00 | 39 | G.O. 38 in 168 of 32 December 1932 | ... | 21,991.52 |
98
(F6)
Return of all Public Works, Civil Roads, Canals, Bridges, Buildings, &c.,—Continued.
Describe the Work, and where situated.
Whether | Estimated Construct-
Expenses
Anthority under
When
Whether Finished
ing or ntuler Repairs.
which it is
Com-
Amount uf
in
executed,
menced,
Dollars.
or Lu- finished.
Expenditure,
PUBLIC WORks ExtraorDINARY,—Conti,
Colonial Estimates 1933.
Head 34 Public Works
G.
COMMUNICATIONS,— Continued,
Extraordinary
DRAINAGE :—
S.H.
Con-
Additional Septic Tank at Repulse Bay,... struction 15,000,00
19
20.7.33
Finished
5,869.79
New Sewer-Wongneicheong Gap to
Island Road in connection with the development of sites along this road,-|
Do.
27,000.00
20
17.5.33
27,000.00
MISCELLANEOUS,
Chinese Cemeteries—laying out new areas.
Colonial Cemetery--laying out new areas,
Do.
6,000,00
21
Anual Vote
་་
5,821.77
Do.
7,000.00
22
"י
**
4,783.98
Tent Tsz Mui Quarry-Covering to mix- ing plants, new high tension cable and a Transformer House,...................
Do.
10,000.00
23
1.1.33 Unfinished
5,881.35
Tsat Tsz Mui Quarry—Extensions and
Improvements,
Do
10,000.00
24
Re-wiring of Government Buildings,
Do.
25,000.00
235
1.1.33
6.191.53
25
Annual Vote Finished
21,245.41
Twelve E. H. T. Disconnecting Joint Boxes for Cable to Cape D'Aguilar,..
Do.
5,700.00)
26
Not commenced Unfinished
3,726.51
Laying telephone cable from the main
route Victoria Gap -Gongh Hill,..
Laying telephone cable between G.P.O.
and Cable Hut at Happy Valley,......
Do.
7,000,000
27
19.10.33 Finished
5,128.92
Do.
42.000.00
28
21.9.33
25,155.78
Reinstatement of Government Retaining
Walls,
Repairs 20,000.00
29
7.11.33 Unfinished
4,314.34
ļ
Central Police Station-Extension to
Store,
Con-
!
struction 1,200.00
30
January Finished
1,189.90
Victoria Hospital-Tennis Court,
Do.
3,000.00
31
March
2,345.96
Victoria Hospital - Hot Water System to
Maternity Block,
Not
Do.
16,000.00
32
Commenced Unfinished)
Central Market-Fish Tanks,
Do.
2,000,00
33
Marchi Finished
1,992.60
Traffic White Lines, Studs, etc.,
Do.
5,000.00
34
Annual Vote
2,279.83
Upper Peak Tram Station Parking Ground,
Do.
6,500 00
35
20.2,33 Unfinished
6,352,44
36
Chai Wan Cemetery Sextons' Quarters, ...
Do.
2,500.00 €.8.0. 781 of 33 September
a
"
Government Pavilion Gardanors' Quarters,
Botanical Gardens—Improvements,.
Do.
800.00
37
Do.
6,600.00
38
October Finished
November
703.32
2,901,38
W
39
Extension to Building Ordinance Office,...
Do.
11.000.00
11,000.00 0.8.0 38in168 of 32 December,
1932
21,991.52
**