Return of all Public Works, Civil Roads, Canals, Bridges, Buildings, &c.,—Continued

Page 74 (F16)

Describe the Work, and where situated Whether Construction or Repairs Estimated Expenses ($) Authority under which it is executed When Commenced Whether Finished or Unfinished Amount of Expenditure ($)
Public Works, Extraordinary,— Contd.
COMMUNICATIONS
Colonial Estimates 1924
Improvements to the junction of Gascoigne and Nathan Roads, Kowloon, cutting away the Hill Construction 122,000.00 C.S.O. 20 in 64 of 1924 ... Finished? 62,387.05
MISCELLANEOUS
Installation of Wireless Telephones at the Water Police Station and Cheung Chau Island Construction 3,600.00 C.S.O. 3944 of 1913 21.3.24 Finished 2,629.86
Installation of Wireless Telegraphy receiving gear at Royal Observatory Construction 2,500.00 C.S.O. 43 of 1915 1.9.24 Finished 1,859.81
... Construction 25,000.00 C.S.O. 3620 of 1924 11.10.23 Finished 45,877.45
Pier, Blackhead's Point Construction 20,000.00 C.S.O. 20 in 63 of 1924 ... ... 377.45
NEW TERRITORIES
Buildings
Extension of the Laichikok Prison and various improvements Construction 35,000.00 C.S.O. 3469 of 1922 16.10.24 Unfinished 33,754.91
COMMUNICATIONS
Improvement to Main Road by Railway Bridge North-West of Taipo Market Construction ... ... ... ... ...
Development of the Road from Taipo Market to Kam Shun Construction ... ... ... ... ...
MISCELLANEOUS
... Construction 20,000.00 C.S.O. 20 in 63 of 1924 ... ... ...
... Construction 3,000.00 C.S.O. 382 of 1924 9.7.24 Finished 3,000.20
... Construction 8,000.00 C.S.O. 560 of 1924 12.5.24 Unfinished 2,000.00
Beacon Light, Cheung Chau Channel Construction 500.00 C.S.O. 8824 of 1904 14.5.24 Finished 10,481.77
Two 2-ton Lorries, New Territories Construction 16,000.00 C.S.O. 3620 of 1924 17.10.24 Finished 16,000.00
Filling in large area near Kowloon City Construction 60,000.00 C.S.O. 3620 of 1924 Oct. 1923 Unfinished 25,214.92

Edit History

2026-07-13 13:12:46 · NVIDIA / nvidia/nemotron-3-ultra-550b-a55b
Live
View comparison
AI Proofread
Return of all Public Works, Civil Roads, Canals, Bridges, Buildings, &c.,—Continued Page 74 (F16) Describe the Work, and where situated Whether Construction or Repairs Estimated Expenses ($) Authority under which it is executed When Commenced Whether Finished or Unfinished Amount of Expenditure ($) Public Works, Extraordinary,— Contd. COMMUNICATIONS Colonial Estimates 1924 Improvements to the junction of Gascoigne and Nathan Roads, Kowloon, cutting away the Hill Construction 122,000.00 C.S.O. 20 in 64 of 1924 ... Finished? 62,387.05 MISCELLANEOUS Installation of Wireless Telephones at the Water Police Station and Cheung Chau Island Construction 3,600.00 C.S.O. 3944 of 1913 21.3.24 Finished 2,629.86 Installation of Wireless Telegraphy receiving gear at Royal Observatory Construction 2,500.00 C.S.O. 43 of 1915 1.9.24 Finished 1,859.81 ... Construction 25,000.00 C.S.O. 3620 of 1924 11.10.23 Finished 45,877.45 Pier, Blackhead's Point Construction 20,000.00 C.S.O. 20 in 63 of 1924 ... ... 377.45 NEW TERRITORIES Buildings Extension of the Laichikok Prison and various improvements Construction 35,000.00 C.S.O. 3469 of 1922 16.10.24 Unfinished 33,754.91 COMMUNICATIONS Improvement to Main Road by Railway Bridge North-West of Taipo Market Construction ... ... ... ... ... Development of the Road from Taipo Market to Kam Shun Construction ... ... ... ... ... MISCELLANEOUS ... Construction 20,000.00 C.S.O. 20 in 63 of 1924 ... ... ... ... Construction 3,000.00 C.S.O. 382 of 1924 9.7.24 Finished 3,000.20 ... Construction 8,000.00 C.S.O. 560 of 1924 12.5.24 Unfinished 2,000.00 Beacon Light, Cheung Chau Channel Construction 500.00 C.S.O. 8824 of 1904 14.5.24 Finished 10,481.77 Two 2-ton Lorries, New Territories Construction 16,000.00 C.S.O. 3620 of 1924 17.10.24 Finished 16,000.00 Filling in large area near Kowloon City Construction 60,000.00 C.S.O. 3620 of 1924 Oct. 1923 Unfinished 25,214.92
Baseline (Original)
74 (F16) Retuan of all Public Works, Civil Roads, Canals, Bridges, Buildings, &c.,—Continued. Describe the Work, and where situated. Whether Estimated Construct. Expenses ing or in nuder Authority under which it is excented. When Com- menced. Repairs. Dollars. Whether Finished or Un- finished. Amount of Expenditure. Public Works, Extraordinary,— Contd. COMMUNICATIONS, .. Colonial Estimates 1924. → Improvements to the junction of Gnseoigne and Nathan Ronds, Kowloon, outting Construc- away the Hill,........ tion. |122,000.00] C.5.0. 20 in 64 $.12,23, of 1924. 62,387.05 Buishel MISCELLANEOUS, Installation of Wireless Telephones at the Water Police Station and Cheung Chan Island, Do. 3,600,00| C.8.0, 3944 of 1913. 21.3.24. Do. 2,629.86- Installation of Wireless Telegraphy rereiv- ing gear at Royal Observatory,. Do. 2,500.00 C.S.O. 43 of 1915. 25,000.00 | 1.8,0, 3620 of 24. 1.9.24. 11.10.23. Do. Finished,, 1,859.81 45,877,45 Pier, Blackhead's Point, Do. 20,000,00 €8,0, 20 in 63 of 24. 377.45 NEW TERRITORIES. Bro.pines. Extension of the Laichikok Prison and varions improvements, COMMUNICATIONS. Improvement to Main Road by Railway Bridge North-West of TaipoMarket, j Development of the Rond from Taipo Market to Kam Shun, MISCELLANEOUS, Do. 35,000,001 | CS,0, 3469 of '22 16.10.24. Un- tinished. 33,754.91 Do. { ,20] C.8.0. 20 in 63 24 3,000,00| C.S.0, 382% of *24 9.7.24. Finished. 3,000,20 Do. 8,000.00 | C.8,0, 560 of 24 12.5.24. Un- finished. 2,000,00 Beacon Light, Cheung Châu Channel,- Do. { 500.00 | 0.8.0, 8824 of '04 10,000.00 14.5.24. Finished. 10,481.77 Two 2-ton Lorries, New Tetritories, Do. 16,000.00 C,S.0, 3620 of *24 17.10.24. Do. 16,000.00 Filling in large area near Kowloon City............ Do. 60,000.00 | C.8,0. 3620 of 24 Oct., 1923. Un- finished. 25.214.92
2026-07-13 13:12:46 · Baseline
View content

74

(F16)

Retuan of all Public Works, Civil Roads, Canals, Bridges, Buildings, &c.,—Continued.

Describe the Work, and where situated.

Whether Estimated Construct.

Expenses ing or

in

nuder

Authority under which it is excented.

When Com- menced.

Repairs.

Dollars.

Whether Finished or Un- finished.

Amount of Expenditure.

Public Works, Extraordinary,— Contd.

COMMUNICATIONS,

..

Colonial

Estimates 1924.

Improvements to the junction of Gnseoigne

and Nathan Ronds, Kowloon, outting Construc- away the Hill,........

tion.

|122,000.00] C.5.0. 20 in 64 $.12,23,

of 1924.

62,387.05

Buishel

MISCELLANEOUS,

Installation of Wireless Telephones at the Water Police Station and Cheung Chan Island,

Do.

3,600,00| C.8.0, 3944 of

1913.

21.3.24.

Do.

2,629.86-

Installation of Wireless Telegraphy rereiv-

ing gear at Royal Observatory,.

Do.

2,500.00

C.S.O. 43 of 1915. 25,000.00 | 1.8,0, 3620 of 24.

1.9.24.

11.10.23.

Do.

Finished,,

1,859.81

45,877,45

Pier, Blackhead's Point,

Do.

20,000,00

€8,0, 20 in 63 of 24.

377.45

NEW TERRITORIES.

Bro.pines.

Extension of the Laichikok Prison and

varions improvements,

COMMUNICATIONS.

Improvement to Main Road by Railway

Bridge North-West of TaipoMarket, j

Development of the Rond from Taipo

Market to Kam Shun,

MISCELLANEOUS,

Do.

35,000,001 | CS,0, 3469 of '22

16.10.24.

Un- tinished.

33,754.91

Do.

{

,20] C.8.0. 20 in 63 24 3,000,00| C.S.0, 382% of *24

9.7.24.

Finished.

3,000,20

Do.

8,000.00 | C.8,0, 560 of 24

12.5.24.

Un- finished.

2,000,00

Beacon Light, Cheung Châu Channel,-

Do. {

500.00 | 0.8.0, 8824 of '04 10,000.00

14.5.24.

Finished.

10,481.77

Two 2-ton Lorries, New Tetritories,

Do.

16,000.00 C,S.0, 3620 of *24

17.10.24.

Do.

16,000.00

Filling in large area near Kowloon City............

Do.

60,000.00 | C.8,0. 3620 of 24 Oct., 1923.

Un- finished.

25.214.92