Colonial Estimates 1922
BUILDINGS
| No. | Description | Type | Estimated Expenses ($) | Authority | Commenced | Status | Expenditure ($) |
|---|---|---|---|---|---|---|---|
| 1 | Officers' Quarters, Quarters for European Officers, Leighton Hill | Construction | 350,000.00 | Colonial Estimates 1922 | 1 Sept. 1921 | Unfinished | 298,228.80 |
| 2 | Quarters for European Officers, Leighton Hill | Construction | 50,000.00 | Colonial Estimates 1922 | Nov. 1921 | Finished | 406,494.13 |
| 3 | Overseer's Quarters, Elliot Filter Beds | Construction | 35,000.00 | Colonial Estimates 1922 | 3 June 1923 | Unfinished | 3,604.50 |
| 4 | D'Aguilar—Erection of Quarters for Office | Construction | 25,000.00 | Colonial Estimates 1922 | 3 June 1923 | Not commenced | 121.66 |
| 5 | Calet Quarters, Canton | Construction | 20,000.00 | Colonial Estimates 1922 | 3 June 1923 | Unfinished | ... |
| 6 | Quarters for Sanitary Inspector, Kennedy Town | Construction | 30,000.00 | Colonial Estimates 1922 | 3 June 1923 | Unfinished | ... |
| 7 | Fire Brigade Station | Construction | 300,000.00 | C.S.O. 20 in 63 of 23 |
Dec. 1921 | Finished | 329,966.57 |
| 8 | Victoria Hospital—Maternity Block and alterations and extensions to existing buildings | Construction | 150,000.00 | C.S.O. 20 in 63 of 23 |
Aug. 1921 | Finished | 167,865.05 |
| 9 | Government Offices—New Offices for Public Works Department | Construction | 50,000.00 | C.S.O. 3200 of '23 |
Feb. 1922 | Finished | 114,109.00 |
| 10 | New Saiyingpun School | Construction | 100,000.00 | Colonial Estimates 1922 | 10 Feb. 1923 | Finished | 75,986.95 |
| 11 | New Queen's College | Construction | 150,000.00 | Colonial Estimates 1922 | Not commenced | Unfinished | 81,309.76 |
| 12 | Hongkong Volunteer Defence Corps Headquarters—Rifle Range | Construction | 5,300.00 | C.S.O. 2341 of '21 |
June 1922 | Finished | 16,214.30 |
| 13 | Alteration to Isolation Building, Kennedy Town | Construction | 10,000.00 | Colonial Estimates 1922 | Not commenced | Unfinished | ... |
| 14 | Extension of Lairage, Kennedy Town | Construction | 20,000.00 | Colonial Estimates 1922 | Not commenced | Unfinished | ... |
| 15 | Extension of Coolie Quarters, Kennedy Town | Construction | 8,000.00 | Colonial Estimates 1922 | Not commenced | Unfinished | ... |
| 16 | Reinstatement of Kennedy Town Police Station | Construction | 10,000.00 | Colonial Estimates 1922 | Not commenced | Unfinished | ... |
| 17 | Saiyingpun Market, Reconstruction | Construction | 50,000.00 | Colonial Estimates 1922 | Not commenced | Unfinished | ... |
| 18 | Government Stores, Extension | Construction | 30,000.00 | Colonial Estimates 1922 | Not commenced | Unfinished | ... |
| 19 | Coal Storage and Motor Garage, Wanchai Depot | Construction | 10,000.00 | Colonial Estimates 1922 | July 1923 | Finished | 9,917.81 |
| 20 | Garage, New Peak Road | Construction | 10,000.00 | C.S.O. 3200 of '23 |
1923 | Finished | 6,298.23 |
| 21 | New Infectious Diseases Hospital | Construction | 30,000.00 | Colonial Estimates 1922 | Not commenced | Unfinished | ... |
| 22 | New Government Offices, Alterations | Construction | 30,000.00 | Colonial Estimates 1922 | Sept. 1923 | Unfinished | 20,169.51 |
| 23 | Old Government Offices, Alterations | Construction | 10,000.00 | C.S.O. 20 in 63 of '23; C.S.O. 3200 of '23 |
June 1923 | Finished | 19,232.31 |
| 24 | Latrines and Urinals | Construction | 25,000.00 | Colonial Estimates 1922 | Jan. 1923 | Continuing work | 8,503.63 |
Cost of stores issued.
+ Cost of Pickets.
Colonial Estimates 1922
BUILDINGS
| No. | Description | Type | Estimated Expenses ($) | Authority | Commenced | Status | Expenditure ($) |
|---|---|---|---|---|---|---|---|
| 1 | Officers' Quarters, Quarters for European Officers, Leighton Hill | Construction | 350,000.00 | Colonial Estimates 1922 | 1 Sept. 1921 | Unfinished | 298,228.80 |
| 2 | Quarters for European Officers, Leighton Hill | Construction | 50,000.00 | Colonial Estimates 1922 | Nov. 1921 | Finished | 406,494.13 |
| 3 | Overseer's Quarters, Elliot Filter Beds | Construction | 35,000.00 | Colonial Estimates 1922 | 3 June 1923 | Unfinished | 3,604.50 |
| 4 | D'Aguilar—Erection of Quarters for Office | Construction | 25,000.00 | Colonial Estimates 1922 | 3 June 1923 | Not commenced | 121.66 |
| 5 | Calet Quarters, Canton | Construction | 20,000.00 | Colonial Estimates 1922 | 3 June 1923 | Unfinished | ... |
| 6 | Quarters for Sanitary Inspector, Kennedy Town | Construction | 30,000.00 | Colonial Estimates 1922 | 3 June 1923 | Unfinished | ... |
| 7 | Fire Brigade Station | Construction | 300,000.00 | C.S.O. 20 in 63 of 23 |
Dec. 1921 | Finished | 329,966.57 |
| 8 | Victoria Hospital—Maternity Block and alterations and extensions to existing buildings | Construction | 150,000.00 | C.S.O. 20 in 63 of 23 |
Aug. 1921 | Finished | 167,865.05 |
| 9 | Government Offices—New Offices for Public Works Department | Construction | 50,000.00 | C.S.O. 3200 of '23 |
Feb. 1922 | Finished | 114,109.00 |
| 10 | New Saiyingpun School | Construction | 100,000.00 | Colonial Estimates 1922 | 10 Feb. 1923 | Finished | 75,986.95 |
| 11 | New Queen's College | Construction | 150,000.00 | Colonial Estimates 1922 | Not commenced | Unfinished | 81,309.76 |
| 12 | Hongkong Volunteer Defence Corps Headquarters—Rifle Range | Construction | 5,300.00 | C.S.O. 2341 of '21 |
June 1922 | Finished | 16,214.30 |
| 13 | Alteration to Isolation Building, Kennedy Town | Construction | 10,000.00 | Colonial Estimates 1922 | Not commenced | Unfinished | ... |
| 14 | Extension of Lairage, Kennedy Town | Construction | 20,000.00 | Colonial Estimates 1922 | Not commenced | Unfinished | ... |
| 15 | Extension of Coolie Quarters, Kennedy Town | Construction | 8,000.00 | Colonial Estimates 1922 | Not commenced | Unfinished | ... |
| 16 | Reinstatement of Kennedy Town Police Station | Construction | 10,000.00 | Colonial Estimates 1922 | Not commenced | Unfinished | ... |
| 17 | Saiyingpun Market, Reconstruction | Construction | 50,000.00 | Colonial Estimates 1922 | Not commenced | Unfinished | ... |
| 18 | Government Stores, Extension | Construction | 30,000.00 | Colonial Estimates 1922 | Not commenced | Unfinished | ... |
| 19 | Coal Storage and Motor Garage, Wanchai Depot | Construction | 10,000.00 | Colonial Estimates 1922 | July 1923 | Finished | 9,917.81 |
| 20 | Garage, New Peak Road | Construction | 10,000.00 | C.S.O. 3200 of '23 |
1923 | Finished | 6,298.23 |
| 21 | New Infectious Diseases Hospital | Construction | 30,000.00 | Colonial Estimates 1922 | Not commenced | Unfinished | ... |
| 22 | New Government Offices, Alterations | Construction | 30,000.00 | Colonial Estimates 1922 | Sept. 1923 | Unfinished | 20,169.51 |
| 23 | Old Government Offices, Alterations | Construction | 10,000.00 | C.S.O. 20 in 63 of '23; C.S.O. 3200 of '23 |
June 1923 | Finished | 19,232.31 |
| 24 | Latrines and Urinals | Construction | 25,000.00 | Colonial Estimates 1922 | Jan. 1923 | Continuing work | 8,503.63 |
Cost of stores issued.
+ Cost of Pickets.
62
(F4)
Return of all Public Works, Civil Roads, Canals, Bridges, Buildings, &c.,-Continued.
Describe the Work, and where situated,
Whether Estimated Construct-i
Expenses
Authority under
ing or under
which it is
in
executed.
When Com- menced.
Whether Finished
Amount
Repairs,
Dollars.
or Un- finished.
of
Expenditure.
PUBLIC WORKS, EXTRAORDINARY.
HONGKONG.
*
¿
Colonial Estimates 1922.
c.
BUILDINGS.
Officers' Quarters,
Construc- tion
350,000.00
1
Sept., 1921.
Un-
finished.
298,228.80
Quarters for European Officers, Leighton
Hill,....
Do.
50,000.00
Nov., 1921, Finished.
406,494.13
Overseer's Quarters, Elliot Filter Beds, ..
Do.
--
35,000.00
3
June, 1923,
Un- finished.
3,604.50
Not
D'Aguilar-Erection of Quarters for Office,
Do.
25,000.00
4
Do.
commenteil.
121.66
Calet Quarters, Canton,
Do.
20,000.00
5
Do.
Do.
KAGING
Quarters for Sanitary Inspector, Kennedy
Town,
Do.
30,000.00
6
Do.
Do.
Fire Brigade Station,...................
Do.
29,966.57 0.8.0. 20 in 63 of 23
Dec.,
*
Do.
300,000,00
1921.
329,966.57
Victoria Hospital,-Maternity Block and
C.S.O. 20 in
alterations and extensions to existing buildings,
Do.
16,884,79
63 of 23
Anga
Do.
167,865,05
| 150,000.00 |
|---|
1921.
8
Government Offices, New Offices for
1,000.00 | 0.8.0. 3200
Feb..
Do.
23,000,0a|
of '23
Finished.
Public Works Department,
1922.
114,109.00
50,000.00)
9
Cn-
New Saiyingpuu School,
Do.
100,000.00|
10
Feb., 1923. finished.
75,986.95
New Queen's College,
Do. 150,000.00
11
Not commenced.
Do.
81,309,76
Hongkong Volunteer Defence Corps [
Head quarters,— Rifle Range,
Do.
5,300.00 €.8.0, 2341 of '21 3,000.00
June, 1922.
Finished.
16,214.30
12
Alteration to Isolation Building, Kennedy
Town,
Not
Do.
10,000.00
13
commcured.
Un- finished.
Extension of Lairage, Kennedy Town,
Do.
20,000 00
1-4
Do.
Do.
Extension of Coolie Quarters, Kennedy
Town,
Do.
8,000.00
15
Do.
Do.
+
11.00
Reinstatement of Kennely Town Police
Station,
Do.
10,000.00,
16
Do.
Do.
Saivingpun Market, Reconstruction,
Do.
50,000.00
17
Do.
Do.
Government Stores, Extension,
Do.
30,000.00
18
Do.
Do.
10.73
Coal Storage and Motor Garage, Wanebai
Depol,
Do.
10,000,00
19
July, 1923.
Dn.
9,917.81
Garage, New Peak Rond,...................
Do.
2,000.00 10,000,00
C.S.O, 3200 of '23
20
{ Do.
Do.
6,298.23
Now Infectious Diseases Hospital,
Do.
30,000.00
Not
Do.
21
commenced.
New Government Officos, Alterations,......
Do.
30,000.00
22
Sept., 1923.
Do.
20,169.51
Okl Government Offices, Alterations,
Do.
2,941.81 |C.S.0), 20 in 63 of '23| 5,500,00|| 0.8.O. 3200 of '29 10,000.00
23
June,
Do.
19,232.31
1923.
Latrinos aml Urinals, .
Do.
25,000.00
24
Jan., 1923. Continuing
8,503.63
work.
Cost of stores issued.
+ Cost of Pickets.
62
(F4)
Return of all Public Works, Civil Roads, Canals, Bridges, Buildings, &c.,-Continued.
Describe the Work, and where situated,
Whether Estimated Construct-i
Expenses
Authority under
ing or under
which it is
in
executed.
When Com- menced.
Whether Finished
Amount
Repairs,
Dollars.
or Un- finished.
of
Expenditure.
PUBLIC WORKS, EXTRAORDINARY.
HONGKONG.
*
¿
Colonial Estimates 1922.
c.
BUILDINGS.
Officers' Quarters,
Construc- tion
350,000.00
1
Sept., 1921.
Un-
finished.
298,228.80
Quarters for European Officers, Leighton
Hill,....
Do.
50,000.00
Nov., 1921, Finished.
406,494.13
Overseer's Quarters, Elliot Filter Beds, ..
Do.
--
35,000.00
3
June, 1923,
Un- finished.
3,604.50
Not
D'Aguilar-Erection of Quarters for Office,
Do.
25,000.00
4
Do.
commenteil.
121.66
Calet Quarters, Canton,
Do.
20,000.00
5
Do.
Do.
KAGING
Quarters for Sanitary Inspector, Kennedy
Town,
Do.
30,000.00
6
Do.
Do.
Fire Brigade Station,...................
Do.
29,966.57 0.8.0. 20 in 63 of 23
Dec.,
*
Do.
300,000,00
1921.
329,966.57
Victoria Hospital,-Maternity Block and
C.S.O. 20 in
alterations and extensions to existing buildings,
Do.
16,884,79
63 of 23
Anga
Do.
167,865,05
| 150,000.00 |
|---|
1921.
8
Government Offices, New Offices for
1,000.00 | 0.8.0. 3200
Feb..
Do.
23,000,0a|
of '23
Finished.
Public Works Department,
1922.
114,109.00
50,000.00)
9
Cn-
New Saiyingpuu School,
Do.
100,000.00|
10
Feb., 1923. finished.
75,986.95
New Queen's College,
Do. 150,000.00
11
Not commenced.
Do.
81,309,76
Hongkong Volunteer Defence Corps [
Head quarters,— Rifle Range,
Do.
5,300.00 €.8.0, 2341 of '21 3,000.00
June, 1922.
Finished.
16,214.30
12
Alteration to Isolation Building, Kennedy
Town,
Not
Do.
10,000.00
13
commcured.
Un- finished.
Extension of Lairage, Kennedy Town,
Do.
20,000 00
1-4
Do.
Do.
Extension of Coolie Quarters, Kennedy
Town,
Do.
8,000.00
15
Do.
Do.
+
11.00
Reinstatement of Kennely Town Police
Station,
Do.
10,000.00,
16
Do.
Do.
Saivingpun Market, Reconstruction,
Do.
50,000.00
17
Do.
Do.
Government Stores, Extension,
Do.
30,000.00
18
Do.
Do.
10.73
Coal Storage and Motor Garage, Wanebai
Depol,
Do.
10,000,00
19
July, 1923.
Dn.
9,917.81
Garage, New Peak Rond,...................
Do.
2,000.00 10,000,00
C.S.O, 3200 of '23
20
{ Do.
Do.
6,298.23
Now Infectious Diseases Hospital,
Do.
30,000.00
Not
Do.
21
commenced.
New Government Officos, Alterations,......
Do.
30,000.00
22
Sept., 1923.
Do.
20,169.51
Okl Government Offices, Alterations,
Do.
2,941.81 |C.S.0), 20 in 63 of '23| 5,500,00|| 0.8.O. 3200 of '29 10,000.00
23
June,
Do.
19,232.31
1923.
Latrinos aml Urinals, .
Do.
25,000.00
24
Jan., 1923. Continuing
8,503.63
work.
Cost of stores issued.
+ Cost of Pickets.