Return of all Public Works, Civil Roads, Canals, Bridges, Buildings, &c.—Continued

(F 8)

PUBLIC WORKS, EXTRAORDINARY

Description of Work Construction / Repair Estimated Cost ($) Authority Date Commenced Status Expenditure ($)
Filling in between bridges, Tai Wo Shi Construction 10,000.00 Item 43 Not commenced Unfinished
Further Reclamation at Shamshuipo Construction 730,000.00 Item 44 Mar., 1919 Unfinished 22,990.01
Chinese Cemeteries—Laying out new areas Construction 500.00 Item 45 Jan., 1919 Continuing work 137.11
Telephonic Communication to Police Station Construction 24,000.00 Item 46 13th Feb., 1919 Finished 15,319.04
Miscellaneous Works Construction 10,000.00 Item 47 (C.S.O. 276) Jan., 1919 Continuing work 17,829.25
Compensation and Resumptions (Public Health and Buildings Ordinance 1903) Construction 25,000.00 C.S.O. 13 of 1919 (63 of 1919) 32,574.66
Shamshuipo District—Laying water mains Construction 27,000.00 Item 49 Aug., 1919 Finished 27,057.14

VOTES NOT APPEARING IN THE ESTIMATES

HONGKONG — BUILDINGS

Description of Work Construction / Repair Estimated Cost ($) Authority Date Commenced Status Expenditure ($)
Erection of a Latrine in Duddell Street Construction 2,000.00 C.S.O. 3150 of 1919 Sept., 1919 Finished 1,965.07

COMMUNICATIONS

Description of Work Construction / Repair Estimated Cost ($) Authority Date Commenced Status Expenditure ($)
Deep Water Bay to Taitam Tuk Road—Improvement to adapt for motor traffic, section from Deep Water Bay to Repulse Bay Construction 20,000.00 C.S.O. 533 of 1916 Feb., 1917 Finished 64,070.25

MISCELLANEOUS

Description of Work Construction / Repair Estimated Cost ($) Authority Date Commenced Status Expenditure ($)
Shelter in Children's Playground Construction 2,200.00 29th Aug., 1918 Finished 3,794.59
Erection of a Car Shelter at Deep Water Bay Construction 2,400.00 C.S.O. 1822 of 1913 (C.S.O. 651 of 1918) 15th July, 1918 Finished 6,637.23
Addition and Alteration to Shaukiwan Police Station Construction 9,000.00 C.S.O. 19 of 1919 July, 1919 Finished 11,825.48
Protection to D'Aguilar Wireless Station Construction 3,500.00 C.S.O. 559 of 1919 June, 1919 Finished 3,339.83
Repairs, alterations, and improvements to Central Police Station Construction 3,900.00 C.S.O. 3 of 1919 (96 of 1919) May, 1919 Finished 8,865.24
Conversion of Berlin Mission Foundling House into Married Police Quarters Construction 3,250.00 C.S.O. 3080 of 1919 September, 1919 Finished 2,208.62
Repairs to Chairs in Council Chamber Repair 530.00 C.S.O. 1841 of 1911 Finished 515.00

WATER WORKS

Description of Work Construction / Repair Estimated Cost ($) Authority Date Commenced Status Expenditure ($)
Tytam Tuk Scheme—Second Suction Construction 1,500.00 (Special Vote for Tests, 1919) C.S.O. 5758 of 1911 22nd Oct., 1912 Finished 2,372,205.12

Note.—Special Vote for Tests of Engines, etc., 1919. The Vote in 1920 is required for the retention money on the Simpson Engines.

Edit History

2026-07-12 22:31:42 · NVIDIA / nvidia/nemotron-3-ultra-550b-a55b
Live
View comparison
AI Proofread
Return of all Public Works, Civil Roads, Canals, Bridges, Buildings, &c.—Continued (F 8) PUBLIC WORKS, EXTRAORDINARY Description of Work Construction / Repair Estimated Cost ($) Authority Date Commenced Status Expenditure ($) Filling in between bridges, Tai Wo Shi Construction 10,000.00 Item 43 Not commenced Unfinished — Further Reclamation at Shamshuipo Construction 730,000.00 Item 44 Mar., 1919 Unfinished 22,990.01 Chinese Cemeteries—Laying out new areas Construction 500.00 Item 45 Jan., 1919 Continuing work 137.11 Telephonic Communication to Police Station Construction 24,000.00 Item 46 13th Feb., 1919 Finished 15,319.04 Miscellaneous Works Construction 10,000.00 Item 47 (C.S.O. 276) Jan., 1919 Continuing work 17,829.25 Compensation and Resumptions (Public Health and Buildings Ordinance 1903) Construction 25,000.00 C.S.O. 13 of 1919 (63 of 1919) — — 32,574.66 Shamshuipo District—Laying water mains Construction 27,000.00 Item 49 Aug., 1919 Finished 27,057.14 VOTES NOT APPEARING IN THE ESTIMATES HONGKONG — BUILDINGS Description of Work Construction / Repair Estimated Cost ($) Authority Date Commenced Status Expenditure ($) Erection of a Latrine in Duddell Street Construction 2,000.00 C.S.O. 3150 of 1919 Sept., 1919 Finished 1,965.07 COMMUNICATIONS Description of Work Construction / Repair Estimated Cost ($) Authority Date Commenced Status Expenditure ($) Deep Water Bay to Taitam Tuk Road—Improvement to adapt for motor traffic, section from Deep Water Bay to Repulse Bay Construction 20,000.00 C.S.O. 533 of 1916 Feb., 1917 Finished 64,070.25 MISCELLANEOUS Description of Work Construction / Repair Estimated Cost ($) Authority Date Commenced Status Expenditure ($) Shelter in Children's Playground Construction 2,200.00 — 29th Aug., 1918 Finished 3,794.59 Erection of a Car Shelter at Deep Water Bay Construction 2,400.00 C.S.O. 1822 of 1913 (C.S.O. 651 of 1918) 15th July, 1918 Finished 6,637.23 Addition and Alteration to Shaukiwan Police Station Construction 9,000.00 C.S.O. 19 of 1919 July, 1919 Finished 11,825.48 Protection to D'Aguilar Wireless Station Construction 3,500.00 C.S.O. 559 of 1919 June, 1919 Finished 3,339.83 Repairs, alterations, and improvements to Central Police Station Construction 3,900.00 C.S.O. 3 of 1919 (96 of 1919) May, 1919 Finished 8,865.24 Conversion of Berlin Mission Foundling House into Married Police Quarters Construction 3,250.00 C.S.O. 3080 of 1919 September, 1919 Finished 2,208.62 Repairs to Chairs in Council Chamber Repair 530.00 C.S.O. 1841 of 1911 — Finished 515.00 WATER WORKS Description of Work Construction / Repair Estimated Cost ($) Authority Date Commenced Status Expenditure ($) Tytam Tuk Scheme—Second Suction Construction 1,500.00 (Special Vote for Tests, 1919) C.S.O. 5758 of 1911 22nd Oct., 1912 Finished 2,372,205.12 Note.—Special Vote for Tests of Engines, etc., 1919. The Vote in 1920 is required for the retention money on the Simpson Engines.
Baseline (Original)
64 (F 8) Return of all Public Works, Civil Roads, Canals, Bridges, Buildings, &c.,—Continued. Whether Estimated ing or Construct Expense Authority under Describe the Work, and where situated. in which it is under Repairs. Dollars. executed. When Com- inenced. Whether Finished AmOUDE of or Un- Expenditura. finished. PUBLIC WORKS, EXTRAORDINARY, —Contď. $ c. Colouinl Estimates 1919. MISCELLANEOUS, Con- Filling in hetween bridges, Tai Wo Shi,................ struction. 10,000,00 43 Not commenced. Un- finished. Further Reclamation at Shamshuipo, Do. 730,000.00 44 Mar., 1919. Do. 22,990.01 Chinese Cemeteries,-Laying out new areas, Do. 500.00 45 Jan., 1919, Continu- ing work. 137.11 Telophonic Communication to Police Station, Do, 24,000.00 46 13th Feb., Finished. 15,319.04 1919. 10,000.00 C.8.0. 276 Jan., Miscellaneous Works, Do. 10,000.00 of 1919, 47 1919. Continuing work. 17,829.25 PUBLIC HEALTH AND Buildings Ordinance 1963. Compensation and Resumptions, 25,000.00 C.S.O. 13 in Do. 20,000.00 63 of 1919. 48 Do. Do. 32,574.66 WATER WORKS, Un- Shamshuipo District,-Laying water mains,. Do. 27,000.00 49 Aug., 1919. finished. 27,057.14 VOTES NOT APPEARING IN THE ESTIMATES. HONGKONG. BUILDINGS. Latrines and Urinals :- Erection of & Latrine in Duddell Street,. Do. 2,000.00 C.S.O. 3150 of 1919. Sept., 1919. Finished. 1,965.07 COMMUNICATIONS. Deep Water Bay to Taitam Tuk Rond,- Improvement to adapt for inotor traffic section from Deep Water Bay to Repulse Bay, 20,000.00 Do. 3,000.00 C.S.O. 533 of 1916. Do. Feb., 1917. Do. 64,070.25 MISCELLANEOUS, Shelter in Children's Playground, Do. 2,200.00 Erection of a Car Shelter at Deep Water Bay, Do. 2,400.00 C.S.O. 1822 of 1913. (C.S.O. 651 of 1918. 15th July, Do. 6,637.23 1918. 29th Ang., Do. 3,794.59 1918. Addition and Alteration to Shaukiwan 9,000,00| C.S.0, 19 in 96 July, Police Station, Do. of 1919. Do. 11,825.48 1919. 2,000.00 Do. Protection to D'Aguilar Wireless Station, Do. 3,500,00{ C.S.O. 559 June, Do. 3,339.83 of 1919. 1919. Repairs, alterations, and improvements to Central Police Station, Do. 3,900.00 J C.S.O. 3 in May, Do. 8,865.24 96 of 1919. 1919. Conversion of Berlin Mission Foundling House into Married Police Quarters, Do. 3,250.00{ C.S.O. 3080 September, Do. 2,208.62 of 1919. 1919. Repairs to Chairs in Council Chamber, Do. 530.00 { C.S.O. 1841 of 1911. * Do. Do. 515.00 Water WORKS, Tytam Tuk Scheme,-Second Suction, C.S.0.5758 **** Do. 1,500.00 of 1911. 22nd Oct., 1912. Do. 2,372,205.12 NOTE,—Special Vote for Tests of Engines, etc., 1919. The Voto in 1920 is required for the retention money on the Simpson Engines.
2026-07-12 22:31:42 · Baseline
View content

64

(F 8)

Return of all Public Works, Civil Roads, Canals, Bridges, Buildings, &c.,—Continued.

Whether Estimated

ing or

Construct Expense Authority under

Describe the Work, and where situated.

in

which it is

under Repairs.

Dollars.

executed.

When Com- inenced.

Whether Finished

AmOUDE of

or Un- Expenditura. finished.

PUBLIC WORKS, EXTRAORDINARY, —Contď.

$ c.

Colouinl Estimates

1919.

MISCELLANEOUS,

Con-

Filling in hetween bridges, Tai Wo Shi,................ struction.

10,000,00

43

Not commenced.

Un- finished.

Further Reclamation at Shamshuipo,

Do.

730,000.00

44

Mar., 1919.

Do.

22,990.01

Chinese Cemeteries,-Laying out new areas,

Do.

500.00

45

Jan., 1919,

Continu- ing work.

137.11

Telophonic Communication to Police Station,

Do,

24,000.00

46

13th Feb., Finished.

15,319.04

1919.

10,000.00

C.8.0. 276

Jan.,

Miscellaneous Works,

Do.

10,000.00

of 1919,

47

1919.

Continuing work.

17,829.25

PUBLIC HEALTH AND Buildings

Ordinance 1963.

Compensation and Resumptions,

25,000.00 C.S.O. 13 in

Do.

20,000.00

63 of 1919. 48

Do.

Do.

32,574.66

WATER WORKS,

Un-

Shamshuipo District,-Laying water mains,.

Do.

27,000.00

49

Aug., 1919. finished. 27,057.14

VOTES NOT APPEARING IN

THE ESTIMATES.

HONGKONG.

BUILDINGS.

Latrines and Urinals :-

Erection of & Latrine in Duddell Street,.

Do.

2,000.00

C.S.O. 3150 of 1919.

Sept., 1919.

Finished.

1,965.07

COMMUNICATIONS.

Deep Water Bay to Taitam Tuk Rond,-

Improvement to adapt for inotor traffic section from Deep Water Bay to Repulse Bay,

20,000.00

Do.

3,000.00

C.S.O. 533 of 1916.

Do.

Feb., 1917.

Do.

64,070.25

MISCELLANEOUS,

Shelter in Children's Playground,

Do.

2,200.00

Erection of a Car Shelter at Deep Water Bay,

Do.

2,400.00

C.S.O. 1822 of 1913. (C.S.O. 651

of 1918.

15th July,

Do.

6,637.23

1918.

29th Ang.,

Do.

3,794.59

1918.

Addition and Alteration to Shaukiwan

9,000,00| C.S.0, 19 in 96

July,

Police Station,

Do.

of 1919.

Do.

11,825.48

1919.

2,000.00

Do.

Protection to D'Aguilar Wireless Station,

Do.

3,500,00{

C.S.O. 559

June,

Do.

3,339.83

of 1919.

1919.

Repairs, alterations, and improvements to

Central Police Station,

Do.

3,900.00

J

C.S.O. 3 in

May,

Do.

8,865.24

96 of 1919.

1919.

Conversion of Berlin Mission Foundling House into Married Police Quarters,

Do.

3,250.00{

C.S.O. 3080 September,

Do.

2,208.62

of 1919.

1919.

Repairs to Chairs in Council Chamber,

Do.

530.00 {

C.S.O. 1841 of 1911.

*

Do.

Do.

515.00

Water WORKS,

Tytam Tuk Scheme,-Second Suction,

C.S.0.5758

****

Do.

1,500.00

of 1911.

22nd Oct., 1912.

Do.

2,372,205.12

  • NOTE,—Special Vote for Tests of Engines, etc., 1919. The Voto in 1920 is required for the retention money on the Simpson Engines.