1913 — Page 93

Blue Books 香港計冊 All

(F9)

CANALS, Bridges, buildingS, &c.,—Continued.

If Finished, actual

Fund from which

the Expense in defrayed.

When Commenced.

Whether Finished or Unfinished.

Revenue of the Colony.

A mount of Expenditure

in Dollars.

If Unfinished, Amount of Expenditure for the year

1913.

REMARKS.

C.

G.

May, 1912.

Finished.

22,393,56

Aug..

1912.

Do.

5,982,86

Sept., 1912.

Do.

10,945.64

Total Expenditure $40,945,64. A further sum of $8,813.29 re- mains to be paid in

1914.

July, 1912.

Do.

11,529.41

Feb., 1913.

Unfinished.

70,508.35

Not begun.

May, 1913, Finished.

3,351,26

April, 1913.

Do.

6,200.40

1912. Unfinished.

345.25

Aug., 1912,

Finished.

11,712.67

Oct., 1913.

Unfinished.

890,12

Do.

Do.

A

616.89

July, 1913.

Finished.

777.39

Sept., 1912.

Do.

1,076.16

Do.

Do.

1,281.95

Buf

June, 1918. Unfinished.

Jan., 1913.

Do.

11,373,61

10,125,31

Retention money $462.45 still to be paid.