A commencement was made to replace and improve certain of the existing works under the RENEWALS AND IMPROVEMENTS FUND and details thereof are given later in this Report. Work was delayed somewhat by late delivery of plant from England due to lack of shipping consequent upon the outbreak of war.

15. The works carried out under PUBLIC WORKS EXTRAORDINARY and WORKS NOT APPEARING IN ESTIMATES were mainly in connection with water services necessary for other offices and are detailed later in this Report.

16. Good progress was made under the LOAN SCHEDULE with the construction of new works the majority of which have been authorized to make up deficiencies in catchment area, filtration, service reservoir and distribution capacities for the present raw water resources. Photographs of some of these works are attached to this Report. Investigations, for further resources, involving surveys, borings and prickings for dam foundations were carried out in the Tai Lam Chung Valley.

17. Under the head of "OTHER WORKS" new pedestal hydrants were fixed for the Fire Brigade.

18. Details of Waterworks Revenue and Expenditure are given in the accounts but comparisons with previous years cannot be made owing to changes in the system.

III.

WATERWORKS RECURRENT.

(1) MAINTENANCE OF WATERWORKS.

(A) ISLAND.

Hours of Supply.

19. The hours of supply were as follows:---

Period. Hours of supply per day. Total number of days. 17th-19th February
23rd May-11th June
14th-30th June
2nd and 4th July. - 42 1st and 3rd July 18 hours
4 a.m. - 10 p.m. 2 5th July - 29th August 17 hours
5 a.m. - 10 p.m. 57 1st September - 31st December 15 hours
6 a.m. - 9 p.m. 178 13th - 22nd May 10 hours
6-11 a.m. and 4-9 p.m. 10 22nd April-12th May
12th and 13th June
30th and 31st August 8 hours 25 1st January-16th February
20th February - 21st April 4-8 p.m. 108

Full supply was thus maintained for 42 days compared with 226 days in 1938.

Edit History

2026-05-10 14:30:22 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 63 14. A commencement was made to replace and improve certain of the existing works under the RENEWALS AND IMPROVEMENTS FUND and details thereof are given later in this Report. Work was delayed somewhat by late delivery of plant from England due to lack of shipping consequent upon the outbreak of war. 15. The works carried out under PUBLIC WORKS EXTRAORDINARY and WORKS NOT APPEARING IN ESTIMATES were mainly in connection with water services necessary for other offices and are detailed later in this Report. 16. Good progress was made under the LOAN SCHEDULE with the construction of new works the majority of which have been authorized to make up deficiencies in catchment area, filtration, service reservoir and distribution capacities for the present raw water resources. Photographs of some of these works are attached to this Report. Investigations, for further resources, involving surveys, borings and prickings for dam foundations were carried out in the Tai Lam Chung Valley. 17. Under the head of "OTHER WORKS" new pedestal hydrants were fixed for the Fire Brigade. 18. Details of Waterworks Revenue and Expenditure are given in the accounts but comparisons with previous years cannot be made owing to changes in the system. III. WATERWORKS RECURRENT. (1) MAINTENANCE OF WATERWORKS. (A) ISLAND. Hours of Supply. 19. The hours of supply were as follows:--- Period. Hours of supply per day. Total number of days. 17th-19th February23rd May-11th June14th-30th June2nd and 4th July. - 42 1st and 3rd July 18 hours4 a.m. - 10 p.m. 2 5th July - 29th August 17 hours5 a.m. - 10 p.m. 57 1st September - 31st December 15 hours6 a.m. - 9 p.m. 178 13th - 22nd May 10 hours6-11 a.m. and 4-9 p.m. 10 22nd April-12th May12th and 13th June30th and 31st August 8 hours 25 1st January-16th February20th February - 21st April 4-8 p.m. 108 Full supply was thus maintained for 42 days compared with 226 days in 1938.
Baseline (Original)
Q 63 14. A commencement was made to replace and improve certain of the existing works under the RENEWALS AND IMPROVEMENTS FUND and details thereof are given later in this Report. Work was delayed somewhat by late delivery of plant from England due to lack of shipping consequent upon the outbreak of war. 15. The works carried out under PUBLIC WORKS EXTRAORDINARY and WORKS NOT APPEARING IN ESTIMATES were mainly in connection with water services necessary for other offices and are detailed later in this Report. 16. Good progress was made under the LOAN SCHEDULE with the construction of new works the majority of which have been authorized to make up deficiencies in catchment area, filtration, service reservoir and distribution capacities for the present raw water resources. Photographs of some of these works are attached to this Report. Investigations, for further resources, involving surveys, borings and prickings for dam foundations were carried out in the Tai Lam Chung Valley. 17. Under the head of "OTHER WORKS" new pedestal hydrants were fixed for the Fire Brigade. 18. Details of Waterworks Revenue and Expenditure are given in the accounts but comparisons with previous years cannot be made owing to changes in the system. III. WATERWORKS RECURRENT. (1) MAINTENANCE OF WATERWORKS. (A) ISLAND. Hours of Supply. 19. The hours of supply were as follows:--- Hours of supply Period. per day. Total number of days. Full supply 17th 19th February 23rd May 11th June 14th 30th June - 2nd and 4th July. 42 18 hours 4 a.m. 17 hours 1st and 3rd July 2 - 10 p.m. 5th July - 29th August 5 a.m. - 10 p.m. 1st September - 31st December 178 15 hours 6 a.m. 10 hours 13th - 22nd May 10 9 p.m. 22nd April 12th May 6- 11 a.m. 12th and 13th June 4-9 p.m. 30th and 31st August 25 8 hours 1st January 16th February 6 - 10 a.m. 20th February - 21st April 108 4-8 p.m. Full supply was thus maintained for 42 days compared with 226 days in 1938.
2026-05-10 14:30:22 · Baseline
View content

Q 63

14.

A commencement was made to replace and improve certain of the existing works under the RENEWALS AND IMPROVEMENTS FUND and details thereof are given later in this Report. Work was delayed somewhat by late delivery of plant from England due to lack of shipping consequent upon the outbreak of war.

15. The works carried out under PUBLIC WORKS EXTRAORDINARY and WORKS NOT APPEARING IN ESTIMATES were mainly in connection with water services necessary for other offices and are detailed later in this Report.

16. Good progress was made under the LOAN SCHEDULE with the construction of new works the majority of which have been authorized to make up deficiencies in catchment area, filtration, service reservoir and distribution capacities for the present raw water resources. Photographs of some of these works are attached to this Report. Investigations, for further resources, involving surveys, borings and prickings for dam foundations were carried out in the Tai Lam Chung Valley.

17. Under the head of "OTHER WORKS" new pedestal hydrants were fixed for the Fire Brigade.

18. Details of Waterworks Revenue and Expenditure are given in the accounts but comparisons with previous years cannot be made owing to changes in the system.

III.

WATERWORKS RECURRENT.

(1) MAINTENANCE OF WATERWORKS.

(A) ISLAND.

Hours of Supply.

19. The hours of supply were as follows:---

Hours of supply

Period.

per day.

Total number of days.

Full supply

17th 19th February

23rd May 11th June

14th 30th June

-

2nd and 4th July.

42

18 hours

4 a.m.

17 hours

1st and 3rd July

2

-

10 p.m.

5th July - 29th August

5 a.m.

-

10 p.m.

1st September - 31st December

178

15 hours

6 a.m.

10 hours

13th - 22nd May

10

9 p.m.

22nd April 12th May

6- 11 a.m.

12th and 13th June

4-9 p.m.

30th and 31st August

25

8 hours

1st January 16th February

6 - 10 a.m.

20th February - 21st April

108

4-8 p.m.

Full supply was thus maintained for 42 days compared with 226 days in 1938.