PORT WORKS.

143. North Point-Reclamation Extension:-This work was referred to in paragraph 141 of last year's report. No work was carried out during the year with the exception of the supervision of the placing of free deposits of filling material. The only large item of expenditure was payment of $3,000 retention money to The Ching Hing Construction Co.

Expenditure
$3,443.64

144. Kennedy Town-Construction of Sea Wall and Cattle Pier:-This work was referred to in paragraph 143 of last year's report. No work was carried out during the year with the exception of the supervision of the placing of free deposits of filling material.

Expenditure
$280.00

BUILDINGS ORDINANCE.

145. Compensation and Resumptions:-Minor street widening and resumptions in connection with development schemes were effected.

Expenditure
$7,187.40

ANTI-MALARIAL WORKS.

146. Anti-Malarial Works:-Work was completed during July in the area between the two reservoirs at Aberdeen. The length of main channel trained was 1,603 feet, varying in diameter from 30" to 18". Work under the contract covering an area at Pokfulam, between the Queen Mary Hospital and Sandy Bay, was continued. 4,953 feet of channel were trained in this area, varying in diameter from 45" to 12". Reference to these two works was made in paragraph 146 of last year's report.

Expenditure
$47,608.30

KOWLOON.

BUILDINGS.

147. New Mental Hospital:—It was decided not to proceed with this work.

Expenditure
Nil:

148. New Ward Block D, Kowloon Hospital:-It was decided not to proceed with this work, and the only expenditure incurred was in connection with site survey.

Expenditure
$105.23

149. Coal Bins, Yaumati Slipway:-It was not possible to proceed with this work, but drawings were in course of preparation towards the end of the year.

Expenditure
Nil.

GENERAL WORKS.

150. Roads:--Works carried out under this head included the kerbing and channelling of portions of eleven roads. Footpaths were paved with granolithic paving and the necessary improvements made in front of new buildings erected during the year.

Edit History

2026-05-10 10:33:46 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 29 PORT WORKS. 143. North Point-Reclamation Extension:-This work was referred to in paragraph 141 of last year's report. No work was carried out during the year with the exception of the supervision of the placing of free deposits of filling material. The only large item of expenditure was payment of $3,000 retention money to The Ching Hing Construction Co. Expenditure$3,443.64 144. Kennedy Town-Construction of Sea Wall and Cattle Pier:-This work was referred to in paragraph 143 of last year's report. No work was carried out during the year with the exception of the supervision of the placing of free deposits of filling material. Expenditure$280.00 BUILDINGS ORDINANCE. 145. Compensation and Resumptions:-Minor street widening and resumptions in connection with development schemes were effected. Expenditure$7,187.40 ANTI-MALARIAL WORKS. 146. Anti-Malarial Works:-Work was completed during July in the area between the two reservoirs at Aberdeen. The length of main channel trained was 1,603 feet, varying in diameter from 30" to 18". Work under the contract covering an area at Pokfulam, between the Queen Mary Hospital and Sandy Bay, was continued. 4,953 feet of channel were trained in this area, varying in diameter from 45" to 12". Reference to these two works was made in paragraph 146 of last year's report. Expenditure$47,608.30 KOWLOON. BUILDINGS. 147. New Mental Hospital:—It was decided not to proceed with this work. ExpenditureNil: 148. New Ward Block D, Kowloon Hospital:-It was decided not to proceed with this work, and the only expenditure incurred was in connection with site survey. Expenditure$105.23 149. Coal Bins, Yaumati Slipway:-It was not possible to proceed with this work, but drawings were in course of preparation towards the end of the year. ExpenditureNil. GENERAL WORKS. 150. Roads:--Works carried out under this head included the kerbing and channelling of portions of eleven roads. Footpaths were paved with granolithic paving and the necessary improvements made in front of new buildings erected during the year.
Baseline (Original)
Q 29 PORT WORKS. 143. North Point-Reclamation Extension:-This work was referred to in paragraph 141 of last year's report. No work was carried out during the year with the exception of the supervision of the placing of free deposits of filling material. The only large item of expenditure was payment of $3,000 retention money to The Ching Hing Construction Co. Expenditure $3,443.64 144. Kennedy Town-Construction of Sea Wall and Cattle Pier:-This work was referred to in paragraph 143 of last year's report. No work was carried out during the year with the exception of the supervision of the placing of free deposits of filling material. Expenditure $280.00 BUILDINGS ORDINANCE. 145. Compensation and Resumptions:-Minor street widening and resumptions in connection with development schemes were effected. Expenditure $7,187.40 ANTI-MALARIAL WORKS. 146. Anti-Malarial Works:-Work was completed during July in the area between the two reservoirs at Aberdeen. The length of main channel trained was 1,603 feet, varying in diameter from 30" to 18". Work under the contract covering an area at Pokfulam, between the Queen Mary Hospital and Sandy Bay, was continued. 4,953 feet of channel were trained in this area, varying in diameter from 45" to 12". Reference to these two works was made in paragraph 146 of last year's report. Expenditure KOWLOON. BUILDINGS. $47,608.30 147. New Mental Hospital:—It was decided not to proceed with this work. Expenditure Nil: 148. New Ward Block D, Kowloon Hospital:-It was decided not to proceed with this work, and the only expenditure incurred was in connection with site survey. Expenditure $105.23 149. Coal Bins, Yaumati Slipway:-It was not possible to proceed with this work, but drawings were in course of preparation towards the end of the year. Expenditure GENERAL WORKS. Nil. 150. Roads:--Works carried out under this head included the kerbing and channelling of portions of eleven roads. Footpaths were paved with granolithic paving and the necessary improvements made in front of new buildings erected during the year.
2026-05-10 10:33:46 · Baseline
View content

Q 29

PORT WORKS.

143. North Point-Reclamation Extension:-This work was referred to in paragraph 141 of last year's report. No work was carried out during the year with the exception of the supervision of the placing of free deposits of filling material. The only large item of expenditure was payment of $3,000 retention money to The Ching Hing Construction Co.

Expenditure

$3,443.64

144. Kennedy Town-Construction of Sea Wall and Cattle Pier:-This work was referred to in paragraph 143 of last year's report. No work was carried out during the year with the exception of the supervision of the placing of free deposits of filling material.

Expenditure

$280.00

BUILDINGS ORDINANCE.

145. Compensation and Resumptions:-Minor street widening and resumptions in connection with development schemes were effected.

Expenditure

$7,187.40

ANTI-MALARIAL WORKS.

146. Anti-Malarial Works:-Work was completed during July in the area between the two reservoirs at Aberdeen. The length of main channel trained was 1,603 feet, varying in diameter from 30" to 18". Work under the contract covering an area at Pokfulam, between the Queen Mary Hospital and Sandy Bay, was continued. 4,953 feet of channel were trained in this area, varying in diameter from 45" to 12". Reference to these two works was made in paragraph 146 of last year's report.

Expenditure

KOWLOON.

BUILDINGS.

$47,608.30

147. New Mental Hospital:—It was decided not to proceed with this work.

Expenditure

Nil:

148. New Ward Block D, Kowloon Hospital:-It was decided not to proceed with this work, and the only expenditure incurred was in connection with site

survey.

Expenditure

$105.23

149. Coal Bins, Yaumati Slipway:-It was not possible to proceed with this work, but drawings were in course of preparation towards the end of the year.

Expenditure

GENERAL WORKS.

Nil.

150. Roads:--Works carried out under this head included the kerbing and channelling of portions of eleven roads. Footpaths were paved with granolithic paving and the necessary improvements made in front of new buildings erected during the year.