122. Traffic White Lines, Studs and Motor Signs, etc.: - For motor traffic purposes the painting of white lines and the laying of aluminium studs on public highways were carried out
Expenditure
$ 3,872.87
123. Colonial Cemetery-Laying out new areas: - No expenditure was incurred during the year.
Expenditure
$ Nil
124. Latrines for two new Bathing Beaches-South of Repulse Bay: - The work consisted of the erection, in brickwork, of latrines at Middle Beach and South Beach. The contract was let to Messrs. Tak Hing & Co. on July 10th, 1935, and was completed satisfactorily on October 30th, 1935.
Expenditure
$ 4,306.18
125. Sanitary Department Garage, Additional Exits: - The question of providing these additional exits was re-considered during the year and it was decided not to execute the work.
Expenditure
$ Nil
126. Cold Storage Rooms at Central Medical Store in Old Seamen's Institute, Wanchai: - This work consisted of the fitting up of an existing room at the Central Medical Store as a Cold Storage Chamber. A contract for the bricking up of existing window openings, the provision of cork insulation to floor, walls and ceiling, the fixing of shelves and the installation of refrigerating plant was let to Messrs. Jardine Engineering Corporation Limited on the 30th May and was completed satisfactorily on the 22nd August and handed over to the Medical Department.
Expenditure
$ 7,612.45
127. Garage Accommodation at Shaukiwan Police Station: - This work was re-considered during the year with a view to the execution of a large scheme and the original proposals were not executed.
Expenditure
$ Nil
128. Chinese Cemeteries laying out new area: - Works carried out under this head is covered by paragraph 36 of the Report.
Expenditure
$ 5,706.64
WATER WORKS.
129. Back Lane Service Pipes: - 1,022 feet of 1" to 2" wrought iron piping were laid as subsidiary mains in back lanes and seventy-nine houses were connected to these and existing subsidiary mains.
Expenditure
$ 1,379.71
-0 40
122. Traffic White Lines, Studs and Motor Signs, etc. :- For motor traffic purposes the painting of white lines and the laying of aluminium studs on public highways were carried out
Expenditure
$ 3,872.87
123. Colonial Cemetery-Laying out new areas:-No ex- penditure was incurred during the year.
Expenditure
$ Nil
124. Latrines for two new Bathing Beaches-South of Repulse Boy:-The work consisted of the erection, in brickwork, of latrines at Middle Beach and South Beach. The contract was let to Messrs. Tak Hing & Co. on July 10th, 1935, and was com- pleted satisfactorily on October 30th, 1935.
Expenditure
$ 4,306.18
125. Sanitary Department Garage, Additional Exits:-The question of providing these additional exits was re-considered during the year and it was decided not to execute the work.
Expenditure
$ Nil
126. Cold Storage Rooms at Central Medical Store in Old Seamen's Institute, Wanchai:-This work consisted of the fitting up of an existing room at the Central Medical Store as a Cold Storage Chamber. A contract for the bricking up of existing window openings, the provision of cork insulation to floor, walls and ceiling, the fixing of shelves and the installation of refrigerat- ing plant was let to Messrs. Jardine Engineering Corporation Limited on the 30th May and was completed satisfactorily o. the 22nd August and handed over to the Medical Department.
.$ 7,612.45
Expenditure
127. Garage Accommodation at Shaukiwan Police Station: -This work was re-considered during the year with a view to the execution of a large scheme and the original proposals were not executed.
Expenditure
$ Nil
128. Chinese Cemeteries laying out new area:-Works carried out under this head is covered by paragraph 36 of the Report.
Expenditure
$ 5,706.64
WATER WORKS.
129. Back Lane Service Pipes:-1,022 feet of 1" to 2" wrought iron piping were laid as subsidiary mains in back lanes and seventy-nine houses were connected to these and existing subsidiary mains.
Expenditure
$ 1,379.71-